Exam 4: Projects
Exam 1: Introduction78 Questions
Exam 2: Strategy56 Questions
Exam 3: Design of Products and Services71 Questions
Exam 4: Projects108 Questions
Exam 5: Strategic Capacity Management69 Questions
Exam 6: Learning Curves57 Questions
Exam 7: Manufacturing Processes52 Questions
Exam 8: Facility Layout60 Questions
Exam 9: Service Processes71 Questions
Exam 10: Waiting Line Analysis and Simulation77 Questions
Exam 11: Process Design and Analysis67 Questions
Exam 12: Six Sigma Quality70 Questions
Exam 13: Statistical Quality Control64 Questions
Exam 14: Lean Supply Chains85 Questions
Exam 15: Logistics, Distribution, and Transportation61 Questions
Exam 16: Global Sourcing and Procurement73 Questions
Exam 17: The Internet of Things and Erp40 Questions
Exam 18: Forecasting102 Questions
Exam 19: Sales and Operations Planning61 Questions
Exam 20: Inventory Management104 Questions
Exam 21: Material Requirements Planning91 Questions
Exam 22: Workcenter Scheduling125 Questions
Select questions type
A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for Activity C?
(Multiple Choice)
4.7/5
(78)
The second step in managing a project is writing the statement of work.
(True/False)
5.0/5
(73)
In a Gantt chart, the horizontal axis is usually which of the following?
(Multiple Choice)
4.8/5
(78)
Upper-level management must decide between pure, functional, and matrix structures as ways to organize projects.
(True/False)
4.8/5
(88)
If a single estimate of the time required to complete an activity is not reliable, the best procedure is to use a mean and standard deviation (or variance) for each activity.
(True/False)
4.9/5
(90)
Which of the following is not a disadvantage of a pure project?
(Multiple Choice)
4.9/5
(72)
One of the disadvantages of a pure project organizational structure is that the project manager has full authority over the project.
(True/False)
5.0/5
(78)
A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWP for Activity A?
(Multiple Choice)
4.8/5
(71)
The fact that organizations are flattening is one of the reasons that project management is important.
(True/False)
4.8/5
(85)
A group of activities combined to be assignable to a single organizational unit is:
(Multiple Choice)
4.7/5
(68)
A tracking Gantt chart superimposes the current schedule onto a baseline plan so deviations are easily noticed.
(True/False)
4.9/5
(76)
You have just used the network planning model for a county road resurfacing project and found the critical path length is 40 days and the standard deviation of the critical path is 10 days. Suppose you want to pick a time (in days) within which you will complete the project with 90% confidence level. What should be that time (in days and round to the nearest whole number)?
(Multiple Choice)
4.8/5
(82)
A simple project listing of five activities and their respective time estimates are presented here:
Using CPM, which activities make up the critical path?
(Multiple Choice)
4.8/5
(69)
Which of the following is not a disadvantage of a functional project?
(Multiple Choice)
5.0/5
(72)
The hierarchy of project tasks, subtasks, and work packages is:
(Multiple Choice)
4.8/5
(75)
This is a further subdivision of a project. It is usually not longer than several months in duration and is performed by one group or organization.
(Multiple Choice)
4.7/5
(79)
One of the assumptions made using CPM is that project activity sequence relationships can be specified and networked.
(True/False)
4.8/5
(91)
A simple project listing of five activities, their predecessors, and their respective time estimates are presented here:
Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)?
(Multiple Choice)
4.9/5
(77)
A work breakdown structure is used in project management but it is not used when the critical path method is involved.
(True/False)
4.8/5
(71)
Which of the following is not an advantage of a pure project?
(Multiple Choice)
5.0/5
(69)
Showing 41 - 60 of 108
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)