Exam 4: Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

In this structure, each project uses people from different functional areas. A dedicated project manager decides what tasks need to be performed and when, but the functional managers control which people to use.

(Multiple Choice)
5.0/5
(84)

You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here. You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project direct costs are given here. <sub> </sub>   The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day,What is the total (i.e., direct and indirect) project cost? The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day,What is the total (i.e., direct and indirect) project cost?

(Multiple Choice)
4.9/5
(78)

One of the advantages of a functional project organizational structure is that a team member can work on several projects.

(True/False)
4.9/5
(66)

You are looking at a chart that has the terms BCWS, BCWP, and AC indicating lines on the chart. What kind of chart are you looking at?

(Multiple Choice)
4.8/5
(89)

In this structure, team members are assigned from the functional units of the organization. The team members remain a part of their functional units and typically are not dedicated to the project.

(Multiple Choice)
4.9/5
(67)

A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the cost performance index for the project?

(Multiple Choice)
4.7/5
(64)

Functional projects have high levels of team member motivation.

(True/False)
4.9/5
(82)

A structure for organizing a project where a self-contained team works full time on the project is:

(Multiple Choice)
4.7/5
(91)

In CPM analysis, it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following?

(Multiple Choice)
4.8/5
(93)

For an activity in a CPM analysis, the early finish time is 20 and the late finish time is 20. Which of the following statements is true?

(Multiple Choice)
4.9/5
(85)

What is a work breakdown structure?

(Multiple Choice)
4.8/5
(87)

The critical path in a CPM analysis is found by locating the activities times with zero slack.

(True/False)
4.8/5
(69)

Earned value management (EVM) has the capability to combine measurements of scope, schedule, and cost in a project.

(True/False)
5.0/5
(85)

A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWP for Activity D?

(Multiple Choice)
4.8/5
(72)

A specific event in a project is:

(Multiple Choice)
4.8/5
(76)

A project milestone is a specific event to be reached by a particular point in time.

(True/False)
4.8/5
(84)

Which of the following is not an advantage of a functional project?

(Multiple Choice)
4.9/5
(86)

A project can be subdivided into which of the following?

(Multiple Choice)
4.7/5
(79)

Slack activity time is the difference between the early start and the late finish of a project activity time.

(True/False)
4.8/5
(69)

A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for the project?

(Multiple Choice)
4.8/5
(83)
Showing 61 - 80 of 108
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)