Exam 4: Projects
Exam 1: Introduction78 Questions
Exam 2: Strategy56 Questions
Exam 3: Design of Products and Services71 Questions
Exam 4: Projects108 Questions
Exam 5: Strategic Capacity Management69 Questions
Exam 6: Learning Curves57 Questions
Exam 7: Manufacturing Processes52 Questions
Exam 8: Facility Layout60 Questions
Exam 9: Service Processes71 Questions
Exam 10: Waiting Line Analysis and Simulation77 Questions
Exam 11: Process Design and Analysis67 Questions
Exam 12: Six Sigma Quality70 Questions
Exam 13: Statistical Quality Control64 Questions
Exam 14: Lean Supply Chains85 Questions
Exam 15: Logistics, Distribution, and Transportation61 Questions
Exam 16: Global Sourcing and Procurement73 Questions
Exam 17: The Internet of Things and Erp40 Questions
Exam 18: Forecasting102 Questions
Exam 19: Sales and Operations Planning61 Questions
Exam 20: Inventory Management104 Questions
Exam 21: Material Requirements Planning91 Questions
Exam 22: Workcenter Scheduling125 Questions
Select questions type
A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for Activity D?
Free
(Multiple Choice)
4.9/5
(78)
Correct Answer:
B
Which of the following is not an advantage of a matrix project?
Free
(Multiple Choice)
4.9/5
(82)
Correct Answer:
A
You have been placed in charge of a large project. Shortened communication lines are required to ensure quick resolution of problems as they arise. You recognize that the project is going to take a lot of time and require a lot of team pride, motivation, and commitment by all members. Which project management structure should you use in this situation?
Free
(Multiple Choice)
5.0/5
(83)
Correct Answer:
A
Using the time-cost CPM model, the crash time is the shortest possible time allowed for each activity in the project.
(True/False)
4.8/5
(87)
The critical path in a project is that sequence of activities that consume the longest amount of time in a project network of activities.
(True/False)
4.9/5
(68)
For an activity in a CPM analysis, the early start time is 8 and the late start time is 10. Which of the following statements is true?
(Multiple Choice)
4.7/5
(76)
A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for Activity A?
(Multiple Choice)
4.8/5
(90)
You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values. What can you conclude?
(Multiple Choice)
4.9/5
(71)
A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWP for Activity B?
(Multiple Choice)
4.7/5
(81)
A disadvantage of a matrix project organizational structure is that a project manager is held responsible for successful completion of the project.
(True/False)
4.9/5
(82)
The critical path in a CPM analysis is always the shortest path through the network.
(True/False)
4.9/5
(81)
This is usually a written description of the objectives to be achieved, with a brief statement of the work to be done and a proposed schedule specifying the start and completion dates.
(Multiple Choice)
4.8/5
(79)
A simple project listing of five activities, their predecessors, and their respective time estimates are presented here:
Using the CPM, which activities have slack in this project?
(Multiple Choice)
4.8/5
(79)
You have just used the network planning model and found the critical path length is 30 days and the variance of the critical path is 25 days. The probability that the project will be completed in 33 days or less is equal to (2 decimal accuracy).
(Multiple Choice)
4.7/5
(87)
A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the schedule performance index for the project?
(Multiple Choice)
4.8/5
(77)
In the time-cost CPM model, cost is assumed to be a linear function of time.
(True/False)
4.7/5
(80)
Which of the following is a graphic project report used in project management?
(Multiple Choice)
4.9/5
(86)
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented here:
Using CPM, which activities have slack in this project?
(Multiple Choice)
5.0/5
(84)