Exam 22: Workcenter Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The term "dependent events" refers to a process sequence.

Free
(True/False)
4.9/5
(79)
Correct Answer:
Verified

True

For a continuous-process type of manufacturing, which of the following is the typical production scheduling approach?

Free
(Multiple Choice)
4.8/5
(79)
Correct Answer:
Verified

A

Assume you are sequencing jobs using Johnson's rule. A particular job requires 3 hours to assemble and then is followed by 2 hours in the painting department. Which of the following is where you would schedule this job?

Free
(Multiple Choice)
5.0/5
(86)
Correct Answer:
Verified

B

According to the theory of constraints, a non-bottleneck is any resource where capacity is less than the demand placed on it.

(True/False)
4.9/5
(74)

Most process are both labor- and machine-limited.

(True/False)
4.9/5
(77)

Assume you are sequencing jobs using Johnson's rule. There are three jobs called A, B, and C. The first step is assembling and the second step is painting. Job A requires 3 hours to assemble and 6 hours to paint. Job B requires 7 hours to assemble and 2 hours to paint. Job C requires 4 hours to assemble and 1 hour to paint. The objective is to minimize the total processing time of all jobs, using Johnson's rule. What is the completion time of the last job in the sequence in the second step (painting)?

(Multiple Choice)
4.8/5
(77)

Since there are so many nonbottleneck operations, an hour saved on them is very valuable.

(True/False)
4.8/5
(78)

When work is scheduled in detail using the setup and run time required for each order, it is called which of the following?

(Multiple Choice)
4.9/5
(76)

Which of the following is not a standard measure of schedule performance that can be used to evaluate priority rules?

(Multiple Choice)
4.8/5
(75)

In a process sequence where a product flows from process A to process B, process A is called the mother process.

(True/False)
4.8/5
(68)

A job has 10 days of processing time left to do before completion, and today is the 5th day of the month. If the job is due on the 15th day of the month, what is its critical ratio?

(Multiple Choice)
4.9/5
(88)

Dr. Eli Goldratt feels that the goal of a firm is to make useful products efficiently.

(True/False)
4.9/5
(89)

According to the theory of constraints, a bottleneck is any resource whose capacity is greater than the demand placed on it.

(True/False)
4.8/5
(71)

One of the principles of workcenter scheduling is that, while certainty of standards, routings, and so forth is not entirely possible in a shop, certainty should always be an objective to work toward.

(True/False)
4.8/5
(76)

In this type of production, the typical scheduling approach is infinite forward scheduling typical: priority control; typically labor-limited, but often machine-limited; often responding to just-in-time orders from customers or MRP due dates.

(Multiple Choice)
4.9/5
(77)

Which of the following is not a priority rule used to schedule the sequence of jobs in a production operation?

(Multiple Choice)
4.7/5
(78)

The goal in developing a service staffing plan is to minimize overtime.

(True/False)
4.8/5
(71)

Which of the following is an approach to dealing with a bottleneck?

(Multiple Choice)
4.8/5
(85)

According to the theory of constraints, throughput is the rate at which product is passed through the manufacturing system.

(True/False)
4.8/5
(77)

An MRP system can allow for product rejects by building a larger batch than is demanded, but a JIT system cannot tolerate poor quality.

(True/False)
4.9/5
(81)