Multiple Choice
You have just used the network planning model for a county road resurfacing project and found the critical path length is 40 days and the standard deviation of the critical path is 10 days. Suppose you want to pick a time (in days) within which you will complete the project with 90% confidence level. What should be that time (in days and round to the nearest whole number) ?
A) 40
B) 13
C) 37
D) 29
E) 53
Correct Answer:

Verified
Correct Answer:
Verified
Q47: One of the disadvantages of a pure
Q48: A project has four activities: A, B,
Q49: The fact that organizations are flattening is
Q50: A group of activities combined to be
Q51: A tracking Gantt chart superimposes the current
Q53: A simple project listing of five activities
Q54: Which of the following is not a
Q55: The hierarchy of project tasks, subtasks, and
Q56: This is a further subdivision of a
Q57: One of the assumptions made using CPM