Exam 16: Scheduling
Exam 1: Introduction to Operations Management74 Questions
Exam 2: Competitiveness, Strategy, and Productivity72 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design76 Questions
Exam 4: Extension: Reliability12 Questions
Exam 5: Strategic Capacity Planning for Products and Services106 Questions
Exam 5: Extension: Decision Theory123 Questions
Exam 6: Process Selection and Facility Layout150 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 7: Extension: Learning Curves68 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 8: Extension: The Transportation Model20 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 10: Extension: Acceptance Sampling65 Questions
Exam 11: Aggregate Planning and Master Scheduling88 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management161 Questions
Exam 14: Jit and Lean Operations87 Questions
Exam 14: Extension: Maintenance38 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming111 Questions
Select questions type
Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):
Job Processing Time ( days ) Due Date (days from now) 2 2 5 6 6 10 3 4 4 8 What is the average completion time for the earliest due date priority rule schedule? Average job tardiness? Average number of jobs at the center?
(Short Answer)
4.7/5
(78)
Determine the processing sequence for the six jobs shown in the following table using Johnson's rule. Calculate total throughput time. Can the makespan be reduced by splitting the latest job? If so, by how much?
Processing Time (hrs) Job ST1 ST2 a 4 6 b 9 8 c 10 5 d 6 9 e 9 7 f 12 10
(Essay)
4.8/5
(78)
A manager must assign four engineers to projects, one to a project. The leader of project C has indicated that he does not want engineer 2 or 3 on his project. Given the following cost figures for each project-engineer combination, and keeping in mind that two combinations are undesirable, determine assignments such that total cost will be minimized.
Engineer 1 \ 18 12 20 19 2 17 18 * 10 3 25 28 * 14 4 28 18 24 25
(Essay)
4.9/5
(70)
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Job Processing Due Time (hrs) (hrs from now) 4 4 3 5 2 2 1 1 If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average job tardiness?
(Multiple Choice)
4.7/5
(79)
A Gantt chart is a basic scheduling tool that is most useful in low-volume systems.
(True/False)
4.9/5
(65)
Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:
Process Time (Hours) Job Center A Center B 4 5 6 6 1 2 5 2 If these jobs were scheduled in the sequence shown, when would idle time occur at machine B?
(Short Answer)
4.9/5
(78)
Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived: Job Processing Time (hrs) Due (hrs from now) 3 5 1 1 4 9 2 3 5 7 If Eva uses the shortest processing time first priority rule to schedule these jobs, what will be the average job tardiness?
(Multiple Choice)
4.8/5
(100)
To facilitate utilization of bottleneck operations, in theory of constraints scheduling ________ can be split into __________ to reduce waiting times.
(Multiple Choice)
4.8/5
(99)
Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived: Job Processing Time (hrs) Due (hrs from now) 3 5 1 1 4 9 2 3 5 7 If Eva uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in her shop today?
(Multiple Choice)
4.7/5
(83)
Use Johnson's rule to determine the optimum processing sequence for the jobs listed in the following table. Chart total throughput time.
Processing Time (mins) Job ST1 ST2 A 20 12 B 10 32 C 8 9 D 14 7 E 5 6 F 18 6
(Essay)
4.7/5
(76)
Scheduling in intermediate-volume systems has three basic issues: run size, timing, and sequence.
(True/False)
4.9/5
(70)
Which of the following is present in the manufacturing scheduling hierarchy but is absent in the service scheduling hierarchy?
(Multiple Choice)
4.9/5
(70)
The assignment method is limited to a maximum of two jobs per resource.
(True/False)
5.0/5
(79)
There are three jobs to be done and three resources with which to do them. Each resource will cost a specific amount to do each job, as shown in the following table:
Machine Job A B C 1 \ 6 9 4 2 4 4 3 3 8 7 4 What is the total cost for the optimum assignment of jobs to machines?
(Short Answer)
5.0/5
(80)
A work center can be a:
(I) machine.
(II) group of machines.
(III) department.
(IV) facility.
(Multiple Choice)
4.7/5
(76)
Given the following information concerning jobs awaiting processing at a single work center, what processing sequence will result if the critical ratio rule is used?
Job Process Time At This Operation (hrs) Process Time At Remaining Operations (hrs) Final Due Date (hrs) 6 4 8 10 15 40 5 10 30 8 12 45 6 8 24
(Essay)
4.8/5
(70)
Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):
Job Processing Time ( days ) Due Date (days from now) 2 2 5 6 6 10 3 4 4 8 What is the average completion time for the shortest processing time priority rule? Average job tardiness? Average number of jobs at the center?
(Short Answer)
4.9/5
(80)
The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body paint work on each are as follows: Car Body Work (hrs) Paint (hrs) A 10 2 B 5 4 C 7 5 D 3 6 E 1 7 Where in the optimum sequence should car A be scheduled?
(Multiple Choice)
4.9/5
(89)
If optimal sequencing through three work centers is desired, Johnson's rule II is used rather than Johnson's rule.