Exam 17: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Prepare a crashing plan for the following project that will reduce the project duration by three weeks. Activity Normal Time (week) Cost for First Crash Cost for Second Crash 1-2 4 12 15 2-4 5 15 15 1-3 5 10 12 3-4 4 8 9 4-5 6 20 20 5-6 3 11 14 6-7 5 12 13 5-7 7 15 16

Free
(Essay)
4.9/5
(84)
Correct Answer:
Verified

First crashed activity is 5-6 for a cost of 11. This reduces overall duration to 22 weeks but creates two critical paths.
There are two ways a second week can be crashed out of this project. Option 1 is to crash activity 4-5 by one week for a cost of 20. The other is to crash activities 3-4 (cost = 8) and 6-7 (cost = 12).
For the third one-week reduction, activity 4-5 must be crashed, for a cost of 20.

Given the network diagram below, determine the probability that the project will finish within 26 weeks of its start. Times on the diagram are in weeks. Given the network diagram below, determine the probability that the project will finish within 26 weeks of its start. Times on the diagram are in weeks.

Free
(Essay)
4.9/5
(76)
Correct Answer:
Verified

 Path  Duration  Std. Dev. z Prob ≤26 weeks 1−2−5−725.002.450.410.65841−4−711.671.007.33≈1.001−3−6−719.331.634.08≈1.00\begin{array}{lllll}\text { Path } & \text { Duration } & \text { Std. Dev. } & z & \text { Prob } \leq 26 \text { weeks } \\\hline 1-2-5-7 & 25.00 & 2.45 & 0.41 & 0.6584 \\1-4-7 & 11.67 & 1.00 & 7.33 & \approx 1.00 \\1-3-6-7 & 19.33 & 1.63 & 4.08 & \approx 1.00\end{array}

Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C - - - A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 What is the estimated standard deviation in the time for activity E?

Free
(Multiple Choice)
4.9/5
(72)
Correct Answer:
Verified

C

There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4. The standard deviation of the critical path is therefore equal to:

(Multiple Choice)
4.9/5
(93)

If two consecutive activities on the same path each have two days of activity slack, this means that each of them can be delayed by two days without delaying the project.

(True/False)
4.9/5
(63)

Activity E has an optimistic time of 9 days, a most likely time of 12 days, and a pessimistic time of 15 days. Estimate its expected time and standard deviation.

(Essay)
4.9/5
(76)

A project has the activities and activity times (days) listed below. Determine the probability that the project will require more than 15 days from start to finish. Activity Exp.Time St.Dev 1-2 6 1.31 2-4 6 2.70 1-3 7 1.00 3-4 6 0.00

(Essay)
4.8/5
(84)

Consider the following work breakdown structure: Start Finish Duration (Days) Activity Node Node Optimistic Most Likely Pessimistic A 1 2 41 50 59 B 1 3 54 60 66 C 2 4 58 70 82 D 3 4 32 41 44 What is the probability that this project will be completed within 130 days?

(Multiple Choice)
4.9/5
(80)

Which of the following would probably not involve the use of PERT?

(Multiple Choice)
4.7/5
(81)

When developing probabilistic estimates of project duration, it is necessary to know which of the following?

(Multiple Choice)
4.9/5
(76)

Which of the following is not a form of risk reduction in project management?

(Multiple Choice)
4.8/5
(75)

To _____ an activity means to shorten the time it will take.

(Multiple Choice)
4.8/5
(82)

Which of the following are advantages of PERT? (I) It is visual. (II) It is automatically updated. (III) Activities that need to be watched closely can be identified.

(Multiple Choice)
4.8/5
(82)

Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C - - - A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 What is the estimated expected (mean) time for project completion?

(Multiple Choice)
4.7/5
(82)

A Gantt chart is built using established precedence relationships.

(True/False)
4.9/5
(74)

The higher the node number, the longer the activity will take.

(True/False)
4.9/5
(93)

Consider the project depicted by the following A-O-A diagram: Consider the project depicted by the following A-O-A diagram:   What is the probability that this project's duration will exceed 8.5 weeks? What is the probability that this project's duration will exceed 8.5 weeks?

(Essay)
4.9/5
(64)

Consider the following work breakdown structure: Time Estimates (wks) Start Finish Activity Node Node A 1 2 11 20 29 B 2 3 2 5 8 C 2 4 18 30 42 D 3 4 7 10 13 E 1 4 31 40 43 What is the estimated expected (mean) time for project completion?

(Multiple Choice)
4.9/5
(74)

Using the information given in the following table: Activity Precedes Duration Start a, b, c - a d 5 d f 6 f g 2 b e 5 e f 9 c h 4 h g, i 6 g end 3 I end 1 (A) Identify the critical path. (B) Determine expected project duration.

(Essay)
4.8/5
(74)

Although PERT and CPM were originally developed for somewhat different types of projects, they are now nearly identical in terms of analysis and procedures.

(True/False)
5.0/5
(76)
Showing 1 - 20 of 137
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)