Exam 17: Project Management
Exam 1: Introduction to Operations Management74 Questions
Exam 2: Competitiveness, Strategy, and Productivity72 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design76 Questions
Exam 4: Extension: Reliability12 Questions
Exam 5: Strategic Capacity Planning for Products and Services106 Questions
Exam 5: Extension: Decision Theory123 Questions
Exam 6: Process Selection and Facility Layout150 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 7: Extension: Learning Curves68 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 8: Extension: The Transportation Model20 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 10: Extension: Acceptance Sampling65 Questions
Exam 11: Aggregate Planning and Master Scheduling88 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management161 Questions
Exam 14: Jit and Lean Operations87 Questions
Exam 14: Extension: Maintenance38 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming111 Questions
Select questions type
Consider the following work breakdown structure: Duration Estimate (Days) Start Finish Activity Node Node Optimistic Most Likely Pessimistic A 1 2 9 15 21 B 1 3 13 21 23 C 2 4 6 9 18 D 2 5 23 35 47 E 3 5 19 26 27 F 4 6 23 29 41 G 5 6 14 20 26 H 6 7 2 5 8 Within what amount of time (in weeks) is there a 90 percent probability that the critical path for this project will be completed? 95 percent? 99 percent?
(Short Answer)
4.9/5
(81)
The standard deviation of the critical path is equal to the sum of the standard deviations of all of the activities on the critical path.
(True/False)
4.9/5
(82)
The task of identifying risks should involve everyone associated with the project.
(True/False)
4.9/5
(75)
Consider the following work breakdown structure: Duration Estimate (Days) Start Finish Activity Node Node Optimistic Most Likely Pessimistic A 1 2 9 15 21 B 1 3 13 21 23 C 2 4 6 9 18 D 2 5 23 35 47 E 3 5 19 26 27 F 4 6 23 29 41 G 5 6 14 20 26 H 6 7 2 5 8 What is the estimated standard deviation (in weeks) for the critical path completion time?
(Short Answer)
4.7/5
(66)
Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C - - - A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 What is the probability that this project will be completed within 205 days?
(Multiple Choice)
4.8/5
(70)
Which of the following are limitations of PERT?
(I) Time estimates may include a fudge factor.
(II) Important activities may be overlooked.
(III) It is an after-the-fact analysis.
(Multiple Choice)
4.8/5
(85)
If the expected length of a path is more than 2.5 standard deviations less than a desired project completion time, the path will not be a factor in assessing the probability of finishing the project on time.
(True/False)
4.8/5
(65)
Consider the following work breakdown structure: Start Finish Duration (Days) Activity Node Node Optimistic Most Likely Pessimistic A 1 2 41 50 59 B 1 3 54 60 66 C 2 4 58 70 82 D 3 4 32 41 44 What is the estimated standard deviation in the time for activity D?
(Multiple Choice)
4.7/5
(78)
Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Optimistic Most Likely Pessimistic Start U, V - - - U W 35 50 65 V W, X 28 40 52 W Z 26 35 44 X Y 28 40 52 Y Z 26 29 38 Z End 36 60 84 What is the estimated expected (mean) time for activity Y?
(Multiple Choice)
5.0/5
(77)
Project risk events tend to be unlikely __________ a project, but that's also when they tend to be the __________.
(Multiple Choice)
4.9/5
(79)
The project computing algorithm requires both a forward and a backward pass.
(True/False)
4.8/5
(85)
The path in a network with the average length of time to completion is called the critical path.
(True/False)
4.8/5
(70)
A project is represented by the following diagram:
The critical path for the network shown is:
(Multiple Choice)
4.9/5
(90)
Activity D has an optimistic time of three days, a pessimistic time of nine days, and a most likely time of four days. Determine its expected time and variance.
(Essay)
4.9/5
(64)
The earliest finish time for an activity is equal to the latest finish time minus the activity time.
(True/False)
4.7/5
(84)
Suppose a project is subject to the following risk events (each with a given probability of occurring and a cost associated with that occurrence): Event Probability Cost (\ 000) I .2 53 II .6 54 III .1 12 IV .3 21 Given these, Event _____ should probably get the most attention and Event _____ should probably get the least.
(Multiple Choice)
5.0/5
(72)
Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C - - - A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 What is the estimated slack time for activity A?
(Multiple Choice)
4.8/5
(82)