Consider the following work breakdown structure: Duration Estimate (Days) Start Finish Activity Node Node Optimistic Most Likely Pessimistic A 1 2 9 15 21 B 1 3 13 21 23 C 2 4 6 9 18 D 2 5 23 35 47 E 3 5 19 26 27 F 4 6 23 29 41 G 5 6 14 20 26 H 6 7 2 5 8 Within what amount of time (in weeks) is there a 90 percent probability that the critical path for this project will be completed? 95 percent? 99 percent?

(Short Answer)
4.9/5
(81)

Concerning PERT and CPM:

(Multiple Choice)
4.7/5
(82)

The standard deviation of the critical path is equal to the sum of the standard deviations of all of the activities on the critical path.

(True/False)
4.9/5
(82)

The task of identifying risks should involve everyone associated with the project.

(True/False)
4.9/5
(75)

Consider the following work breakdown structure: Duration Estimate (Days) Start Finish Activity Node Node Optimistic Most Likely Pessimistic A 1 2 9 15 21 B 1 3 13 21 23 C 2 4 6 9 18 D 2 5 23 35 47 E 3 5 19 26 27 F 4 6 23 29 41 G 5 6 14 20 26 H 6 7 2 5 8 What is the estimated standard deviation (in weeks) for the critical path completion time?

(Short Answer)
4.7/5
(66)

Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C - - - A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 What is the probability that this project will be completed within 205 days?

(Multiple Choice)
4.8/5
(70)

Which of the following are limitations of PERT? (I) Time estimates may include a fudge factor. (II) Important activities may be overlooked. (III) It is an after-the-fact analysis.

(Multiple Choice)
4.8/5
(85)

If the expected length of a path is more than 2.5 standard deviations less than a desired project completion time, the path will not be a factor in assessing the probability of finishing the project on time.

(True/False)
4.8/5
(65)

Consider the following work breakdown structure: Start Finish Duration (Days) Activity Node Node Optimistic Most Likely Pessimistic A 1 2 41 50 59 B 1 3 54 60 66 C 2 4 58 70 82 D 3 4 32 41 44 What is the estimated standard deviation in the time for activity D?

(Multiple Choice)
4.7/5
(78)

Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Optimistic Most Likely Pessimistic Start U, V - - - U W 35 50 65 V W, X 28 40 52 W Z 26 35 44 X Y 28 40 52 Y Z 26 29 38 Z End 36 60 84 What is the estimated expected (mean) time for activity Y?

(Multiple Choice)
5.0/5
(77)

Project risk events tend to be unlikely __________ a project, but that's also when they tend to be the __________.

(Multiple Choice)
4.9/5
(79)

The project computing algorithm requires both a forward and a backward pass.

(True/False)
4.8/5
(85)

The path in a network with the average length of time to completion is called the critical path.

(True/False)
4.8/5
(70)

A project is represented by the following diagram: A project is represented by the following diagram:   The critical path for the network shown is: The critical path for the network shown is:

(Multiple Choice)
4.9/5
(90)

Activity D has an optimistic time of three days, a pessimistic time of nine days, and a most likely time of four days. Determine its expected time and variance.

(Essay)
4.9/5
(64)

The earliest finish time for an activity is equal to the latest finish time minus the activity time.

(True/False)
4.7/5
(84)

Suppose a project is subject to the following risk events (each with a given probability of occurring and a cost associated with that occurrence): Event Probability Cost (\ 000) I .2 53 II .6 54 III .1 12 IV .3 21 Given these, Event _____ should probably get the most attention and Event _____ should probably get the least.

(Multiple Choice)
5.0/5
(72)

The basis for use of the beta distribution in PERT is:

(Multiple Choice)
4.9/5
(74)

Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C - - - A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 What is the estimated slack time for activity A?

(Multiple Choice)
4.8/5
(82)

Slack time is equal to LS-ES or LF-EF.

(True/False)
4.9/5
(91)