Consider the following work breakdown structure: Duration Estimate (Days) Start Finish Activity Node Node Optimistic Most Likely Pessimistic A 1 2 9 15 21 B 1 3 13 21 23 C 2 4 6 9 18 D 2 5 23 35 47 E 3 5 19 26 27 F 4 6 23 29 41 G 5 6 14 20 26 H 6 7 2 5 8 What are the estimated slack times (in weeks) for activities A-H?

(Short Answer)
4.8/5
(82)

Given this information about activity 3-4: ES = 10, EF = 15, LS = 16, and LF = 21, we can determine that the amount of slack associated with the activity is:

(Multiple Choice)
4.7/5
(81)

Most likely time generally is more than optimistic time.

(True/False)
4.7/5
(76)

A popular tool for planning and scheduling simple projects, and for initial planning on more complex projects, is the:

(Multiple Choice)
4.9/5
(67)

A sequence of activities that leads from the starting node to the finishing node is called a:

(Multiple Choice)
4.7/5
(89)

The network diagram describes sequential relationships among major activities on a project.

(True/False)
4.8/5
(68)

In the project network presented below, numbers on each arrow refer to the expected time and standard deviation in weeks for that particular activity. For example, "8,2" indicates an activity with an expected time of 8 and a standard deviation of two weeks. In the project network presented below, numbers on each arrow refer to the expected time and standard deviation in weeks for that particular activity. For example, 8,2 indicates an activity with an expected time of 8 and a standard deviation of two weeks.   For this project, determine each of the following: (A) the activities which are on the critical path (B) the expected project duration (C) the probability that the project will be completed in 29 weeks or less For this project, determine each of the following: (A) the activities which are on the critical path (B) the expected project duration (C) the probability that the project will be completed in 29 weeks or less

(Essay)
4.8/5
(86)

A hierarchical listing of what must be done in a project is called a:

(Multiple Choice)
4.8/5
(74)

Consider the following work breakdown structure: Duration Estimate (Days) Start Finish Activity Node Node Optimistic Most Likely Pessimistic A 1 2 9 15 21 B 1 3 13 21 23 C 2 4 6 9 18 D 2 5 23 35 47 E 3 5 19 26 27 F 4 6 23 29 41 G 5 6 14 20 26 H 6 7 2 5 8 What is the probability that the critical path for this project will be completed within 75 weeks? 80 weeks? 85 weeks? 90 weeks?

(Short Answer)
4.9/5
(79)

Consider the following work breakdown structure: Time Estimates (wks) Start Finish Activity Node Node A 1 2 11 20 29 B 2 3 2 5 8 C 2 4 18 30 42 D 3 4 7 10 13 E 1 4 31 40 43 What is the probability that the critical path for this project will be completed within 52 weeks?

(Multiple Choice)
4.8/5
(69)

A project is represented by the following diagram: A project is represented by the following diagram:   The critical path for the network shown is: The critical path for the network shown is:

(Multiple Choice)
4.8/5
(96)

If an activity is determined to be on the critical path, that means that it, and perhaps others, will affect project:

(Multiple Choice)
4.9/5
(80)

Consider the following work breakdown structure: Activity Precedes Normal Time (wks) Crashing Cost week week) Start A, B - - - A C, D 6 8 - B G 4 5 6 C E 4 - - D F 5 6 6 E H 6 8 8 F H 6 7 10 G I 8 3 5 H End 5 12 15 I End 6 5 - In crashing this project, which activity should be the first to be reduced?

(Short Answer)
4.8/5
(88)

Shortening activity durations is called:

(Multiple Choice)
4.8/5
(90)

The costs associated with risk events tend to be lower near the beginning of a project and higher near the end of the project.

(True/False)
4.9/5
(78)

An advantage of Gantt charts in project management is that they identify which activities can be delayed without delaying the overall project.

(True/False)
4.7/5
(89)

Consider the following work breakdown structure: Time Estimates (wks) Start Finish Activity Node Node A 1 2 11 20 29 B 2 3 2 5 8 C 2 4 18 30 42 D 3 4 7 10 13 E 1 4 31 40 43 What is the estimated expected (mean) time for activity E?

(Multiple Choice)
4.9/5
(72)

At which point does crashing of a project cease?

(Multiple Choice)
4.8/5
(93)

In project network analysis, "slack" refers to the difference between:

(Multiple Choice)
4.9/5
(74)

Path probabilities are calculated by dividing path mean by path standard deviations.

(True/False)
4.9/5
(74)