Exam 17: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A project is represented by the following diagram: A project is represented by the following diagram:   The expected duration of this project is: The expected duration of this project is:

(Multiple Choice)
4.8/5
(67)

Consider the following work breakdown structure: Activity Precedes Normal Time (wks) Crashing Cost week) week) Start A, B - - - A C, D 6 8 - B G 4 5 6 C E 4 - - D F 5 6 6 E H 6 8 8 F H 6 7 10 G I 8 3 5 H End 5 12 15 I End 6 5 - What is the total cost of reducing the project to 18 weeks?

(Short Answer)
4.9/5
(78)

Activity J has a duration of 7 and an earliest finish time of 21. If J's latest start time is 16, this must mean that J's slack is:

(Multiple Choice)
4.9/5
(70)

Which of the following is not an element of the project management triangle?

(Multiple Choice)
4.7/5
(88)

The main function of dummy activities is to clarify relationships in network diagrams.

(True/False)
4.8/5
(69)

In a project network, the critical path is the sequence of activities which has the:

(Multiple Choice)
4.9/5
(83)

Project management differs from management of more traditional activities mainly because of: (I) its limited time frame. (II) its unique, defined set of activities. (III) the requirement for use of the appropriate resources. (IV) the need for planning and execution.

(Multiple Choice)
4.8/5
(85)

A project consists of nine major activities, as shown below. There are three separate paths in the network: a-c-f, b-d-g, and e-h-i. (A) What is expected project duration time? (B) Determine the probability that the project will take more than 35 weeks to complete. (All times are in weeks.) Activity Exp. Duration Std.Dev. a 7 1 b 10 1 c 9 2 d 11 2 e 16 2 f 14 2 g 10 2 h 8 1 I 8 2  A project consists of nine major activities, as shown below. There are three separate paths in the network: a-c-f, b-d-g, and e-h-i. (A) What is expected project duration time? (B) Determine the probability that the project will take more than 35 weeks to complete. (All times are in weeks.)   \begin{array} { l l l }  \text { Activity } & \text { Exp. Duration } & \text { Std.Dev. } \\ \hline \text { a } & 7 & 1 \\ \text { b } & 10 & 1 \\ \text { c } & 9 & 2 \\ \text { d } & 11 & 2 \\ \text { e } & 16 & 2 \\ \text { f } & 14 & 2 \\ \text { g } & 10 & 2 \\ \text { h } & 8 & 1 \\ \text { I } & 8 & 2 \end{array}

(Essay)
4.9/5
(77)

Some organizations use a matrix organization to integrate the activities of specialists within a functional framework.

(True/False)
4.9/5
(72)

Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B - - - A C, D 44 50 56 B D 45 60 75 C E 42 45 48 D F 31 40 49 E F 27 36 39 F End 58 70 82 What is the estimated expected (mean) time for activity E?

(Multiple Choice)
4.8/5
(83)

Once a project is underway, the project manager usually is not responsible for effectively managing:

(Multiple Choice)
4.8/5
(77)

Deterministic networks use three time estimates-shortest, most likely, and longest-for each activity in order to best determine the activity's estimated time.

(True/False)
4.9/5
(79)

Consider the following work breakdown structure: Start Finish Duration (Days) Activity Node Node Optimistic Most Likely Pessimistic A 1 2 41 50 59 B 1 3 54 60 66 C 2 4 58 70 82 D 3 4 32 41 44 What is the estimated expected (mean) time for project completion?

(Multiple Choice)
4.9/5
(72)

Consider the following work breakdown structure: Time Estimates (wks) Start Finish Activity Node Node A 1 2 11 20 29 B 2 3 2 5 8 C 2 4 18 30 42 D 3 4 7 10 13 E 1 4 31 40 43 What is the estimated slack time for activity E?

(Multiple Choice)
4.9/5
(70)

In the probabilistic approach to project network analysis, the time estimate annotated tm for any activity is the:

(Multiple Choice)
4.8/5
(80)

Which of the following is not typically treated as part of a project life cycle?

(Multiple Choice)
4.7/5
(79)

The probability that the project will go beyond the desired time is equal to one minus the joint probability that all paths will be completed within the desired time.

(True/False)
5.0/5
(69)
Showing 121 - 137 of 137
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)