Exam 17: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A disadvantage of activity-on-node diagrams is the occasional need for dummy activities.

(True/False)
4.9/5
(72)

What is the probability that this project will take more than 10 weeks to complete if the activity means and standard deviations are as shown below? Activity Mean Std.Dev. 1-2 5 1 2-3 4 1 1-3 8 1

(Essay)
4.8/5
(76)

A PERT/CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:

(Multiple Choice)
4.9/5
(70)

Many activities have slack time; if we add these slack times together, this represents the potential improvement in early completion for the project.

(True/False)
4.9/5
(90)

Consider the following work breakdown structure: Duration Estimates (Days) Activity Precedes Optimistic Most Likely Pessimistic Start U, V - - - U W 35 50 65 V W, X 28 40 52 W Z 26 35 44 X Y 28 40 52 Y Z 26 29 38 Z End 36 60 84 What is the estimated slack time for activity W?

(Multiple Choice)
4.9/5
(76)

Consider the following work breakdown structure: Duration Estimate (Days) Start Finish Activity Node Node Optimistic Most Likely Pessimistic A 1 2 9 15 21 B 1 3 13 21 23 C 2 4 6 9 18 D 2 5 23 35 47 E 3 5 19 26 27 F 4 6 23 29 41 G 5 6 14 20 26 H 6 7 2 5 8 What is the critical path for this project network?

(Short Answer)
4.8/5
(73)

Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B - - - A C, D 44 50 56 B D 45 60 75 C E 42 45 48 D F 31 40 49 E F 27 36 39 F End 58 70 82 What is the estimated standard deviation in the time for activity E?

(Multiple Choice)
4.8/5
(79)

Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B - - - A C, D 44 50 56 B D 45 60 75 C E 42 45 48 D F 31 40 49 E F 27 36 39 F End 58 70 82 What is the estimated expected (mean) time for project completion?

(Multiple Choice)
4.7/5
(72)

The earliest finish time for an activity is equal to the latest finish time minus the activity slack.

(True/False)
4.9/5
(80)

Gantt charts are most closely associated with

(Multiple Choice)
4.9/5
(84)

Activity 7-8 is directly preceded by two activities-activity 5-7 and activity 6-7. Activity 5-7 has an expected time of five and an ES time of six. Activity 6-7 has an expected time of seven and an ES time of seven. Activity 7-8 has an expected time of 10. The ES for activity 7-8 is:

(Multiple Choice)
4.8/5
(90)

Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days. Its expected time (in days) is approximately:

(Multiple Choice)
4.9/5
(87)

Which of the following is not characteristic of good risk management?

(Multiple Choice)
4.7/5
(87)

A project is represented by the following diagram: A project is represented by the following diagram:   The expected duration of this project is: The expected duration of this project is:

(Multiple Choice)
4.8/5
(72)

Which of the following is not true about the use of dummy activities in project networking?

(Multiple Choice)
4.8/5
(73)

A hierarchical (vertical) listing of what must be done during a project is called matrix.

(True/False)
4.8/5
(82)

Consider the following work breakdown structure: Duration Estimate (Days) Start Finish Activity Node Node Optimistic Most Likely Pessimistic A 1 2 9 15 21 B 1 3 13 21 23 C 2 4 6 9 18 D 2 5 23 35 47 E 3 5 19 26 27 F 4 6 23 29 41 G 5 6 14 20 26 H 6 7 2 5 8 What is the estimated expected (mean) time (in weeks) for project completion?

(Short Answer)
4.9/5
(95)

A method used for establishing a logical framework for identifying the required activities for the project is called:

(Multiple Choice)
4.8/5
(71)

The sum of times of the longest path in a network indicates expected project completion time, and the activities represent the critical activities.

(True/False)
4.9/5
(77)

The latest starting time for an activity is equal to the latest finish time minus the activity time.

(True/False)
5.0/5
(74)
Showing 21 - 40 of 137