Exam 17: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

In order to determine the probability of timely project completion, it is sometimes necessary to take into account paths other than the critical path.

(True/False)
4.7/5
(86)

Consider the following work breakdown structure: Activity Precedes Normal Time (wks) Crashing Cost week) week) Start A, B - - - A C, D 6 8 - B G 4 5 6 C E 4 - - D F 5 6 6 E H 6 8 8 F H 6 7 10 G I 8 3 5 H End 5 12 15 I End 6 5 - What is the total cost of reducing this project by two weeks?

(Short Answer)
4.8/5
(79)

The total cost of crashing any one activity should never exceed 20 percent of the total cost of the original project.

(True/False)
4.8/5
(82)

Activities not on the critical path have a slack time equal to zero.

(True/False)
4.8/5
(65)

The advantage a precedence diagram has over a Gantt chart is:

(Multiple Choice)
4.8/5
(74)

Which of the following leads to simulation being a useful tool with uncertain activity times?

(Multiple Choice)
4.9/5
(65)

In the execution phase of a project's life cycle, activities are guided by decisions that were made in the __________ phase.

(Multiple Choice)
4.9/5
(82)

Consider the following work breakdown structure: Duration Estimate (Days) Start Finish Activity Node Node Optimistic Most Likely Pessimistic A 1 2 9 15 21 B 1 3 13 21 23 C 2 4 6 9 18 D 2 5 23 35 47 E 3 5 19 26 27 F 4 6 23 29 41 G 5 6 14 20 26 H 6 7 2 5 8 What are the estimated standard deviations (in weeks) in the times for activities A-H?

(Short Answer)
4.8/5
(80)

Which of the following is not one of the six key decisions in project management? (I) Selecting the project team (II) Deciding on the project manager's title (III) Managing and controlling project resources (IV) Deciding which projects to implement (V) Selecting the project manager

(Multiple Choice)
4.8/5
(80)

Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B, C - - - A D 38 50 62 B E 90 99 108 C End 85 100 115 D F 19 25 31 E End 91 100 115 F End 62 65 68 What is the estimated expected (mean) time for activity E?

(Multiple Choice)
5.0/5
(77)

Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B - - - A C, D 44 50 56 B D 45 60 75 C E 42 45 48 D F 31 40 49 E F 27 36 39 F End 58 70 82 What is the estimated slack time for activity D?

(Multiple Choice)
4.9/5
(78)

Once a project is approved and underway, project managers are only responsible for effectively managing time and costs which, if done well, will assure project completion on time and on budget.

(True/False)
4.8/5
(66)

Consider the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B - - - A C, D 44 50 56 B D 45 60 75 C E 42 45 48 D F 31 40 49 E F 27 36 39 F End 58 70 82 What is the probability that the critical path for this project will be completed within 210 days?

(Multiple Choice)
4.7/5
(91)

There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days. The standard deviation of the critical path is:

(Multiple Choice)
5.0/5
(81)

Consider the portion of a project depicted by this graph: Consider the portion of a project depicted by this graph:   What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23? What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23?

(Multiple Choice)
4.9/5
(87)

The project management strategy of injecting additional resources in order to reduce the length of the project is called:

(Multiple Choice)
4.8/5
(86)

Matrix organizations transfer control of workers to project managers for the duration of the project.

(True/False)
4.8/5
(76)

The probability of occurrence of risk events is lower near the beginning of a project and higher near the end of the project since very few activities remain.

(True/False)
4.9/5
(88)

Consider the following work breakdown structure: Time Estimates (wks) Start Finish Activity Node Node A 1 2 11 20 29 B 2 3 2 5 8 C 2 4 18 30 42 D 3 4 7 10 13 E 1 4 31 40 43 What is the estimated standard deviation in the time for activity E?

(Multiple Choice)
4.9/5
(80)

Which of the following stages is that one in which the project's expected costs, benefits, and risks are assessed?

(Multiple Choice)
4.8/5
(69)
Showing 41 - 60 of 137