Exam 16: Scheduling
Exam 1: Introduction to Operations Management74 Questions
Exam 2: Competitiveness, Strategy, and Productivity72 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design76 Questions
Exam 4: Extension: Reliability12 Questions
Exam 5: Strategic Capacity Planning for Products and Services106 Questions
Exam 5: Extension: Decision Theory123 Questions
Exam 6: Process Selection and Facility Layout150 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 7: Extension: Learning Curves68 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 8: Extension: The Transportation Model20 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 10: Extension: Acceptance Sampling65 Questions
Exam 11: Aggregate Planning and Master Scheduling88 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management161 Questions
Exam 14: Jit and Lean Operations87 Questions
Exam 14: Extension: Maintenance38 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming111 Questions
Select questions type
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Job Processing Due Time (hrs) (hrs from now) 4 4 3 5 2 2 1 1 If he uses the earliest due date first priority rule to schedule these jobs, what will be the average job tardiness?
(Multiple Choice)
4.9/5
(76)
Ensuring that the constraining resource is used to its maximum is an example of constraint:
(Multiple Choice)
4.8/5
(70)
The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows: Project (Hours) Consultant A B C D Charlie 13 16 11 13 Betty 11 15 14 18 Johnny 15 22 12 15 Rick 17 17 12 22 After the row and column reductions, what is the reduced time for assigning Rick to project D?
(Multiple Choice)
5.0/5
(89)
Sequencing is concerned with the order in which jobs are done, while loading is concerned with assigning jobs to work centers or workstations.
(True/False)
4.9/5
(87)
Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived: Job Processing Time (hrs) Due (hrs from now) 3 5 1 1 4 9 2 3 5 7 If Eva uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average completion time?
(Multiple Choice)
4.9/5
(83)
The two different approaches to load work centers in job-shop scheduling are:
(Multiple Choice)
4.9/5
(85)
Which of the following is critical to effective yield management?
(Multiple Choice)
4.8/5
(84)
Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:
Process Time (Hours) Job Center A Center B 4 5 6 6 1 2 5 2 In developing the sequence which will minimize throughput time, where should job X be placed?
(Short Answer)
4.9/5
(67)
In a single work center, makespan improvement can be accomplished by selecting the optimal sequencing rule.
(True/False)
4.8/5
(84)
Job X, which has a duration of four days, is due by the close of business on Friday, December 23. Without looking at the work already scheduled on X's required resource, the scheduler schedules X to be begun on the morning of Tuesday, December 20. This is an example of:
(Multiple Choice)
4.8/5
(71)
In the decision-making hierarchy, scheduling decisions are the final step in the transformation process before actual output occurs.
(True/False)
4.9/5
(81)
Priority rules are used in low-volume systems to identify an optimal processing sequence.
(True/False)
4.9/5
(73)
The priority rule where jobs are processed according to the smallest ratio of due date to processing time is:
(Multiple Choice)
4.9/5
(91)
Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):
Job Processing Time ( days ) Due Date (days from now) 2 2 5 6 6 10 3 4 4 8 What is the schedule sequence using the shortest processing time priority rule?
(Short Answer)
5.0/5
(89)
There are four resources and four jobs to be done. The time required for each resource to do each job is as follows: Job (Hours) Resource 1 5 8 7 7 2 4 9 5 9 3 6 9 8 7 4 7 6 6 9 After the row and column reductions, what is the minimum number of lines needed to cover all of the zeroes?
(Multiple Choice)
5.0/5
(86)
Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):
Job Processing Time ( days ) Due Date (days from now) 2 2 5 6 6 10 3 4 4 8 What is the average completion time for the first come, first served priority rule schedule? Average job tardiness? Average number of jobs at the center?
(Short Answer)
4.8/5
(91)
Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived: Job Processing Time ( hrs ) Due (hrs from now) V 3 5 W 1 1 4 9 2 3 5 7 If Eva uses the first come, first served priority rule to schedule these jobs, what will be the average completion time?
(Multiple Choice)
5.0/5
(80)
Given the information in the table, determine the following:
(A) Processing sequence using (1) SPT and (2) EDD
(B) Average completion time and average job tardiness using (1) SPT and (2) EDD
Job Processing Time (hrs) Hour Due A 17 15 B 10 25 C 5 20 D 7 32 E 11 38
(Essay)
4.8/5
(67)
Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:
Process Time (Hours) Job Center A Center B 4 5 6 6 1 2 5 2 If these jobs were scheduled in the sequence shown, what would be the throughput time?
(Short Answer)