Exam 22: Workcenter Scheduling
Exam 1: Introduction72 Questions
Exam 2: Strategy50 Questions
Exam 4: Project Management72 Questions
Exam 3: Design of Products and Services53 Questions
Exam 5: Strategic Capacity Management57 Questions
Exam 6: Learning Curves55 Questions
Exam 7: Manufacturing Processes41 Questions
Exam 8: Facility Layout55 Questions
Exam 9: Service Processes61 Questions
Exam 10: Waiting Line Analysis and Simulation70 Questions
Exam 11: Process Design and Analysis53 Questions
Exam 12: Six Sigma Quality69 Questions
Exam 13: Statistical Quality Control63 Questions
Exam 14: Lean Supply Chains71 Questions
Exam 15: Logistics Distribution, and Transportation55 Questions
Exam 16: Global Sourcing and Procurement66 Questions
Exam 17: Enterprise Resource Planning Systems45 Questions
Exam 18: Forecasting90 Questions
Exam 19: Sales and Operations Planning61 Questions
Exam 20: Inventory Management102 Questions
Exam 21: Material Requirements Planning83 Questions
Exam 22: Workcenter Scheduling61 Questions
Exam 23: Theory of Constraints55 Questions
Exam 24: Health Care60 Questions
Exam 25: Operations Consulting53 Questions
Select questions type
Which of the following is one of the major functions of shop-floor control?
(Multiple Choice)
4.7/5
(83)
One of the principles of work center scheduling is that the effectiveness of any shop should be measured by speed of flow through the shop.
(True/False)
4.8/5
(94)
Which of the following is a principle of work center scheduling?
(Multiple Choice)
4.9/5
(90)
Which of the following is not a standard measure of schedule performance that can be used to evaluate priority rules?
(Multiple Choice)
4.7/5
(63)
Priority rules are the rules used to obtain a job sequence in production scheduling.
(True/False)
4.9/5
(70)
For a mid-volume type of manufacturing, which of the following is the typical production scheduling approach?
(Multiple Choice)
4.9/5
(82)
Using the random order or "whim" priority rule to sequence production jobs means that supervisors or operators select whichever job they feel like running.
(True/False)
5.0/5
(74)
Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 4 days (i.e., job A will take 4 more days to complete), B will take 7 days, C will take 8 days, D will take 2 days, and E will take 5 days.All jobs are available now and the time now is 0.Using SOT rule sequence the jobs and find the schedule (single machine scheduling problem).What is the completion time of job B as per your schedule?
(Multiple Choice)
4.9/5
(80)
One of the principles of work center scheduling is that, while certainty of standards, routings, and so forth is not entirely possible in a shop, certainty should always be an objective to work toward.
(True/False)
5.0/5
(85)
Which of the following might be a status and exception report used in shop-floor control?
(Multiple Choice)
5.0/5
(81)
For a high-volume type of manufacturing, which of the following is the typical production scheduling approach?
(Multiple Choice)
4.8/5
(68)
The textbook underscores the importance of scheduling with the phrase "workflow equals cash flow, and scheduling lies at the heart of the process."
(True/False)
4.9/5
(72)
For a continuous-process type of manufacturing, which of the following is the typical production scheduling approach?
(Multiple Choice)
4.8/5
(85)
Shop-floor control (or production activity control) can involve expediting late and critical orders.
(True/False)
5.0/5
(73)
Scheduling hourly work times using the "first-hour principle" ensures that no excess labor will be used during the work shift.
(True/False)
4.7/5
(85)
A job has 5 days of processing time left to do before completion, and today is the 10th day of the month.If the job is due on the 14th day of the month, what is its critical ratio?
(Multiple Choice)
4.8/5
(86)
Theoretically, all schedules are feasible when finite loading is used.
(True/False)
4.8/5
(79)
Assume you are sequencing jobs using Johnson's rule.A particular job requires 7 hours to assemble and then is followed by 8 hours in the painting department.Which of the following is where you would schedule this job?
(Multiple Choice)
4.8/5
(72)
Assume you are sequencing jobs using Johnson's rule.There are three jobs called A, B and C.The first step in assembling and the second step is painting. Job A requires 3 hours to assemble and 6 hours to paint.Job B requires 7 hours to assemble and 2 hours to paint.Job C requires 4 hours to assemble and 1 hour to paint.The objective is to minimize the total processing time of all jobs, using Johnson's rule.What is the correct sequence to process the jobs?
(Multiple Choice)
4.9/5
(91)
Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 4 days (i.e., job A will take 4 more days to complete), B will take 7 days, C will take 8 days, D will take 2 days, and E will take 5 days.Which job should be scheduled first if you use the SOT priority rule for job sequencing?
(Multiple Choice)
4.8/5