Assume You Are Sequencing Jobs Using Johnson's Rule

Question 59

Multiple Choice

Assume you are sequencing jobs using Johnson's rule.There are three jobs called A, B and C.The first step in assembling and the second step is painting. Job A requires 3 hours to assemble and 6 hours to paint.Job B requires 7 hours to assemble and 2 hours to paint.Job C requires 4 hours to assemble and 1 hour to paint.The objective is to minimize the total processing time of all jobs, using Johnson's rule.What is the correct sequence to process the jobs?


A) A - C - B
B) B - C - A
C) B - A - C
D) A - B - C
E) C - B - A

Correct Answer: