Exam 22: Workcenter Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The assignment method of job sequencing is a special case of the transportation method of linear programming.

Free
(True/False)
4.9/5
(66)
Correct Answer:
Verified

True

A shop-floor control system is a system that uses data from the shop floor as well as data processing files to maintain and communicate status information on shop orders and work centers.

Free
(True/False)
4.7/5
(80)
Correct Answer:
Verified

True

Johnson's rule, a priority rule used in sequencing production jobs, is used only in production situations where we are dealing with one machine or one stage of production activity.

Free
(True/False)
4.9/5
(88)
Correct Answer:
Verified

False

Which of the following is a tool of shop-floor control?

(Multiple Choice)
4.9/5
(77)

The objective of Johnson's rule for job sequencing is to minimize flow time from the beginning of the first job until the completion of the last job.

(True/False)
4.9/5
(80)

A system that "backward schedules" is designed to determine and report the earliest date an order can be completed.

(True/False)
4.9/5
(61)

For a low-volume job shop type of manufacturing, which of the following is the typical production scheduling approach?

(Multiple Choice)
4.8/5
(76)

Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 3 days (i.e., job A will take 3 more days to complete), B will take 9 days, C will take 6 days, D will take 5 days and E will take 8 days.Which job should be scheduled last if using the SOT priority rule for job sequencing?

(Multiple Choice)
4.8/5
(72)

One of the principles of work center scheduling is to match work center input information to what the worker can actually do.

(True/False)
5.0/5
(75)

The FCFS priority rule used in sequencing production jobs will always result in a better solution than the LCFS rule.

(True/False)
4.9/5
(71)

A backward schedule tells when an order must be started in order to be done by a specific date.

(True/False)
4.8/5
(73)

Assume you are sequencing jobs using Johnson's rule.A particular job requires 3 hours to assemble and then is followed by 2 hours in the painting department.Which of the following is where you would schedule this job?

(Multiple Choice)
4.8/5
(84)

When work is scheduled in detail using the setup and run time required for each order, it is called which of the following?

(Multiple Choice)
4.9/5
(88)

Assume you are sequencing jobs using Johnson's rule.There are three jobs called A, B and C.The first step in assembling and the second step is painting. Job A requires 3 hours to assemble and 6 hours to paint.Job B requires 7 hours to assemble and 2 hours to paint.Job C requires 4 hours to assemble and 1 hour to paint.The objective is to minimize the total processing time of all jobs, using Johnson's rule.What is the completion time of the last job in the sequence in the second step (painting)?

(Multiple Choice)
4.8/5
(89)

Which of the following is a priority rule used to schedule the sequence of jobs in a production operation?

(Multiple Choice)
4.9/5
(83)

The assignment method is useful in solving scheduling problems that have which of the following characteristics?

(Multiple Choice)
4.8/5
(77)

Which of the following is not a function performed in scheduling and controlling an operation?

(Multiple Choice)
4.8/5
(86)

Under the STR/OP sequencing priority rule, orders with the jobs with the longest STR/OP are run first.

(True/False)
4.7/5
(80)

In production scheduling, the process of determining which job to start first on some machine or in some work center is known as sequencing or priority sequencing.

(True/False)
4.8/5
(76)

Which of the following is not one of the major functions of shop-floor control?

(Multiple Choice)
4.7/5
(86)
Showing 1 - 20 of 61