Exam 4: Project Management
Exam 1: Introduction72 Questions
Exam 2: Strategy50 Questions
Exam 4: Project Management72 Questions
Exam 3: Design of Products and Services53 Questions
Exam 5: Strategic Capacity Management57 Questions
Exam 6: Learning Curves55 Questions
Exam 7: Manufacturing Processes41 Questions
Exam 8: Facility Layout55 Questions
Exam 9: Service Processes61 Questions
Exam 10: Waiting Line Analysis and Simulation70 Questions
Exam 11: Process Design and Analysis53 Questions
Exam 12: Six Sigma Quality69 Questions
Exam 13: Statistical Quality Control63 Questions
Exam 14: Lean Supply Chains71 Questions
Exam 15: Logistics Distribution, and Transportation55 Questions
Exam 16: Global Sourcing and Procurement66 Questions
Exam 17: Enterprise Resource Planning Systems45 Questions
Exam 18: Forecasting90 Questions
Exam 19: Sales and Operations Planning61 Questions
Exam 20: Inventory Management102 Questions
Exam 21: Material Requirements Planning83 Questions
Exam 22: Workcenter Scheduling61 Questions
Exam 23: Theory of Constraints55 Questions
Exam 24: Health Care60 Questions
Exam 25: Operations Consulting53 Questions
Select questions type
The critical path in a CPM analysis is always the shortest path through the network.
Free
(True/False)
5.0/5
(77)
Correct Answer:
False
A project can be subdivided into which of the following?
Free
(Multiple Choice)
4.9/5
(87)
Correct Answer:
C
You have just used the network planning model for a county road resurfacing project and found the critical path length is 40 days and the standard deviation of the critical path is 10 days.Suppose you want to pick a time (in days) within which you will complete the project with 90% confidence level, what should be that time (in days and round to the nearest whole number.)
Free
(Multiple Choice)
4.7/5
(82)
Correct Answer:
A
In CPM, the late start time estimate is the latest time you can start an activity and still keep the entire project on schedule.
(True/False)
4.8/5
(79)
Derivative projects are those that address incremental changes to products or processes.
(True/False)
4.8/5
(95)
PERT is an abbreviation for which of the following methodologies?
(Multiple Choice)
4.8/5
(82)
You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values.What can you conclude?
(Multiple Choice)
4.9/5
(85)
Which of the following is a graphic project report used in project management?
(Multiple Choice)
4.7/5
(70)
A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented here:
Using CPM, which activities have slack in this project?
(Multiple Choice)
4.8/5
(83)
A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented here:
Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)?
(Multiple Choice)
4.8/5
(78)
You have the following time and cost information for use in a time-cost CPM scheduling model.
What are the three costs per unit of time to expedite each activity?
(Multiple Choice)
4.8/5
(81)
A listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons?
(Multiple Choice)
4.9/5
(89)
In the time-cost CPM model, cost is assumed to be a linear function of time.
(True/False)
4.8/5
(76)
The activity direct costs associated with a project might include giving workers overtime to complete a project in less than the expected time.
(True/False)
4.9/5
(67)
Breakthrough projects are those that provide fundamental improvements to existing products.
(True/False)
4.9/5
(83)
In a Gantt chart, the horizontal axis is usually which of the following?
(Multiple Choice)
4.8/5
(85)
In a CPM analysis, if you subtract the late finish from the early finish, the result is the activity's slack time.
(True/False)
4.9/5
(92)
In CPM analysis, it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following?
(Multiple Choice)
4.8/5
(83)
Slack activity time is the difference between the early start and the late finish of a project activity time.
(True/False)
4.9/5
(83)
The second step in managing a project is writing the statement of work.
(True/False)
4.8/5
(77)
Showing 1 - 20 of 72
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)