Exam 4: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The critical path in a CPM analysis is always the shortest path through the network.

Free
(True/False)
5.0/5
(77)
Correct Answer:
Verified

False

A project can be subdivided into which of the following?

Free
(Multiple Choice)
4.9/5
(87)
Correct Answer:
Verified

C

You have just used the network planning model for a county road resurfacing project and found the critical path length is 40 days and the standard deviation of the critical path is 10 days.Suppose you want to pick a time (in days) within which you will complete the project with 90% confidence level, what should be that time (in days and round to the nearest whole number.)

Free
(Multiple Choice)
4.7/5
(82)
Correct Answer:
Verified

A

In CPM, the late start time estimate is the latest time you can start an activity and still keep the entire project on schedule.

(True/False)
4.8/5
(79)

Derivative projects are those that address incremental changes to products or processes.

(True/False)
4.8/5
(95)

PERT is an abbreviation for which of the following methodologies?

(Multiple Choice)
4.8/5
(82)

You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values.What can you conclude?

(Multiple Choice)
4.9/5
(85)

Which of the following is a graphic project report used in project management?

(Multiple Choice)
4.7/5
(70)

A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented here: Using CPM, which activities have slack in this project?

(Multiple Choice)
4.8/5
(83)

A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented here: Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)?

(Multiple Choice)
4.8/5
(78)

You have the following time and cost information for use in a time-cost CPM scheduling model. What are the three costs per unit of time to expedite each activity?

(Multiple Choice)
4.8/5
(81)

A listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons?

(Multiple Choice)
4.9/5
(89)

In the time-cost CPM model, cost is assumed to be a linear function of time.

(True/False)
4.8/5
(76)

The activity direct costs associated with a project might include giving workers overtime to complete a project in less than the expected time.

(True/False)
4.9/5
(67)

Breakthrough projects are those that provide fundamental improvements to existing products.

(True/False)
4.9/5
(83)

In a Gantt chart, the horizontal axis is usually which of the following?

(Multiple Choice)
4.8/5
(85)

In a CPM analysis, if you subtract the late finish from the early finish, the result is the activity's slack time.

(True/False)
4.9/5
(92)

In CPM analysis, it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following?

(Multiple Choice)
4.8/5
(83)

Slack activity time is the difference between the early start and the late finish of a project activity time.

(True/False)
4.9/5
(83)

The second step in managing a project is writing the statement of work.

(True/False)
4.8/5
(77)