Exam 20: Inventory Management
Exam 1: Introduction72 Questions
Exam 2: Strategy50 Questions
Exam 4: Project Management72 Questions
Exam 3: Design of Products and Services53 Questions
Exam 5: Strategic Capacity Management57 Questions
Exam 6: Learning Curves55 Questions
Exam 7: Manufacturing Processes41 Questions
Exam 8: Facility Layout55 Questions
Exam 9: Service Processes61 Questions
Exam 10: Waiting Line Analysis and Simulation70 Questions
Exam 11: Process Design and Analysis53 Questions
Exam 12: Six Sigma Quality69 Questions
Exam 13: Statistical Quality Control63 Questions
Exam 14: Lean Supply Chains71 Questions
Exam 15: Logistics Distribution, and Transportation55 Questions
Exam 16: Global Sourcing and Procurement66 Questions
Exam 17: Enterprise Resource Planning Systems45 Questions
Exam 18: Forecasting90 Questions
Exam 19: Sales and Operations Planning61 Questions
Exam 20: Inventory Management102 Questions
Exam 21: Material Requirements Planning83 Questions
Exam 22: Workcenter Scheduling61 Questions
Exam 23: Theory of Constraints55 Questions
Exam 24: Health Care60 Questions
Exam 25: Operations Consulting53 Questions
Select questions type
Which of the following is not included as an inventory holding cost?
(Multiple Choice)
4.9/5
(63)
A company wants to determine its reorder point (R).Demand is variable and the company wants to build a safety stock into R.If the average daily demand is 12, the lead time is 5 days, the desired z value is 1.96, and the standard deviation of usage during lead time is 3, which of the following is the desired value of R?
(Multiple Choice)
4.7/5
(75)
The standard fixed-time-period model assumes that inventory is never counted but determined by EOQ measures.
(True/False)
4.8/5
(93)
Which of the following is the symbol used in the textbook for the cost of placing an order in the fixed-order-quantity inventory model?
(Multiple Choice)
4.8/5
(64)
Which of the following is a perpetual system for inventory management?
(Multiple Choice)
4.9/5
(82)
Using the fixed-time-period inventory model, and given an average daily demand of 15 units, 3 days between inventory reviews, 1 day for lead time, 30 units of inventory on hand, a service probability of 98 percent, and a standard deviation of daily demand is 3 units, which of the following is the order quantity?
(Multiple Choice)
4.7/5
(81)
Which of the following is an assumption of the basic fixed-order-quantity inventory model?
(Multiple Choice)
4.9/5
(85)
If annual demand is 50,000 units, the ordering cost is $25 per order, and the holding cost is $5 per unit per year, which of the following is the optimal order quantity using the fixed-order-quantity model?
(Multiple Choice)
4.9/5
(86)
If it takes a supplier 2 days to deliver an order once it has been placed and the daily demand for 3 days has been 120, 124, and 125, which of the following is the standard deviation of usage during lead time?
(Multiple Choice)
4.8/5
(89)
In a price-break model of lot sizing, to find the lowest-cost order quantity, it is sometimes necessary to calculate the economic order quantity for each possible price.
(True/False)
4.9/5
(68)
One of the drivers of the direct-to-store (direct distribution) approach is the upstream migration of value-added logistics services.
(True/False)
4.8/5
(81)
An inventory system is a set of policies and controls that monitors levels of inventory and determines what levels should be maintained, when stock should be replenished, and how large orders should be.
(True/False)
4.7/5
(75)
One of the drivers of the direct-to-store (direct distribution) approach is the decrease in trucking industry regulation.
(True/False)
4.9/5
(80)
Which of the following are the recommended percentage groupings of the ABC classifications of the dollar volume of products?
(Multiple Choice)
4.8/5
(78)
Safety stock can be defined as the amount of inventory carried in addition to the expected demand.
(True/False)
4.8/5
(77)
Fixed-time-period inventory models generate order quantities that vary from time period to time period, depending on the usage rate.
(True/False)
4.8/5
(71)
To take into consideration demand uncertainty in reorder point (R) calculations, what do we add to the product of the average daily demand and lead time in days when calculating the value of R?
(Multiple Choice)
4.9/5
(77)
A company wants to determine its reorder point (R).Demand is variable and the company wants to build a safety stock into R.The company wants to have a service probability coverage of 95 percent.If average daily demand is 8, lead time is 3 days, and the standard deviation of usage during lead time is 2, which of the following is the desired value of R?
(Multiple Choice)
4.7/5
(79)
In a price-break model of lot sizing, the lowest cost quantity is always feasible.
(True/False)
4.8/5
(82)
Showing 21 - 40 of 102
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)