Exam 6: Project Time Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Which of the following techniques involve doing activities in parallel that one would normally do in sequence?

(Multiple Choice)
4.9/5
(84)

A drawback of the precedence diagramming method is that it cannot be used unless dummy activities are employed.

(True/False)
4.9/5
(81)

In a critical path analysis, the shortest path is what drives the completion date for the project.

(True/False)
4.7/5
(81)

Which of the following is a difference between an activity list and an activity attribute?

(Multiple Choice)
4.8/5
(81)

After defining project activities, the next step in project time management is developing the schedule.

(True/False)
4.9/5
(71)

A(n) _____ for a project is the series of activities that determine the earliest time by which the project can be completed.

(Short Answer)
4.8/5
(91)

In an AOA network diagram, _____ occur when two or more activities follow a single node.

(Multiple Choice)
4.9/5
(75)

What are milestones? Describe.

(Essay)
4.7/5
(79)

In project time management, the process of_____ primarily involves checking and managing changes to the project schedule.

(Multiple Choice)
4.8/5
(59)

A drawback of the project management software is that it does not have the capacity to calculate the critical path(s) for a project.

(True/False)
4.8/5
(72)

The activity list should include the _____, an activity identifier, and a brief description of the activity.

(Short Answer)
4.9/5
(84)

_____ is the number of workdays or work hours required to complete a task.

(Short Answer)
4.8/5
(83)

An activity is an element of work that has an expected duration, cost, and resource requirements.

(True/False)
4.9/5
(82)

A schedule management plan includes information which describes the format and frequency of schedule reports required for the project.

(True/False)
4.8/5
(82)

In project time management, the next step after sequencing activities is to define these activities.

(True/False)
4.8/5
(78)

AOA network diagrams use only _____ dependencies.

(Multiple Choice)
4.8/5
(77)

Network diagrams are the preferred technique for showing activity sequencing.

(True/False)
4.8/5
(62)

_____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.

(Multiple Choice)
4.7/5
(81)

Critical chain scheduling assumes that resources multitask and maximizes multitasking.

(True/False)
4.8/5
(70)

In a network diagram, a(n) _____ is the starting and ending point of an activity.

(Short Answer)
4.7/5
(73)
Showing 81 - 100 of 102