Exam 7: Project Cost Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Describe three tools used in developing a good cost estimate.

Free
(Essay)
4.8/5
(75)
Correct Answer:
Verified

Several tools and techniques can be used to create a cost estimate. Three of such tools are as follows:
(1) Analogous estimates: They use the actual cost of a previous, similar project as the basis for estimating the cost of the current project. This technique requires a good deal of expert judgment and is generally less costly than other techniques, but it is also less accurate. Analogous estimates are most reliable when the previous projects are similar in fact, not just in appearance. In addition, the groups preparing cost estimates must have the needed expertise to determine whether certain parts of the project will be more or less expensive than analogous projects.
(2) Bottom-up estimates: They involve estimating the costs of individual work items or activities and summing them to get a project total. This approach is sometimes referred to as activity-based costing. The size of the individual work items and the experience of the estimators drive the accuracy of the estimates. Using smaller work items increases the accuracy of the cost estimate because the people assigned to do the work develop the cost estimate instead of someone unfamiliar with the work. The drawback with bottom-up estimates is that they are usually time-intensive and therefore expensive to develop.
(3) Parametric estimating: They use project characteristics (parameters) in a mathematical model to estimate project costs. Parametric models are most reliable when the historical information used to create the model is accurate, the parameters are readily quantifiable, and the model is flexible in terms of the project's size.

Schedule variance is:

Free
(Multiple Choice)
4.9/5
(73)
Correct Answer:
Verified

A

The main outputs of the _____ process are activity cost estimates, basis of estimates, and project document updates.

Free
(Short Answer)
4.9/5
(77)
Correct Answer:
Verified

cost estimating

Profits may be defined as:

(Multiple Choice)
4.8/5
(83)

Supporting details for an estimate include the ground rules and assumptions used in creating the estimate.

(True/False)
4.8/5
(80)

A(n) _____ estimate is done very early in a project or even before a project is officially started.

(Short Answer)
4.7/5
(76)

Budgetary estimates are made even before a project is officially started.

(True/False)
4.8/5
(93)

Cost variance is:

(Multiple Choice)
4.8/5
(82)

The _____ is the portion of the approved total cost estimate planned to be spent on an activity during a given period.

(Short Answer)
4.9/5
(88)

What are tangible and intangible costs? Distinguish between direct and indirect costs and give examples of each.

(Essay)
4.9/5
(71)

What are the three basic types of cost estimating? Describe each type.

(Essay)
4.8/5
(70)

Variances are calculated by subtracting the actual cost from _____.

(Multiple Choice)
4.9/5
(97)

In an earned value chart, when the actual cost line is right on or above the earned value line, it indicates that costs are less than planned.

(True/False)
4.7/5
(73)

Contingency reserves are also known as unknown unknowns.

(True/False)
4.8/5
(82)

Which of the following is most likely to be a reason for inaccuracies in information technology cost estimates?

(Multiple Choice)
4.9/5
(74)

The _____ is based on the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to date.

(Short Answer)
4.8/5
(74)

Analogous estimates are the most accurate technique to estimate costs.

(True/False)
4.7/5
(84)

The timeframe for a(n) _____ estimate is often three or more years prior to project completion.

(Short Answer)
4.9/5
(76)

A budgetary estimate is the most accurate of the three types of estimates.

(True/False)
4.8/5
(92)

Estimates should become more accurate as time progresses.

(True/False)
4.9/5
(81)
Showing 1 - 20 of 102
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)