Exam 6: Project Time Management
Exam 1: Introduction to Project Management96 Questions
Exam 2: The Project Management and Information Technology Context89 Questions
Exam 3: The Project Management Process Groups: A Case Study83 Questions
Exam 4: Project Integration Management83 Questions
Exam 5: Project Scope Management77 Questions
Exam 6: Project Time Management102 Questions
Exam 7: Project Cost Management102 Questions
Exam 8: Project Quality Management81 Questions
Exam 9: Project Human Resource Management89 Questions
Exam 10: Project Communications Management74 Questions
Exam 11: Project Risk Management79 Questions
Exam 12: Project Procurement Management83 Questions
Exam 13: Project Stakeholder Management50 Questions
Select questions type
The main disadvantage of crashing is that it lengthens the time needed to finish a project.
Free
(True/False)
4.8/5
(71)
Correct Answer:
False
In project time management, the next step after defining project activities is:
Free
(Multiple Choice)
4.9/5
(91)
Correct Answer:
B
A backward pass through the network diagram determines the early start and early finish dates for each activity.
Free
(True/False)
4.8/5
(75)
Correct Answer:
False
One of the first reality checks on scheduling that a project manager should make is to review the _____.
(Short Answer)
4.8/5
(87)
A network diagramming technique in which boxes represent activities is known as a(n) _____.
(Multiple Choice)
4.9/5
(76)
A dependency pertains to the sequencing of project activities or tasks.
(True/False)
5.0/5
(86)
Which of the following processes in project time management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?
(Multiple Choice)
4.7/5
(83)
In project time management, which of the following processes generate the main outputs of an activity list, activity attributes, and a milestone list?
(Multiple Choice)
4.7/5
(75)
The technique of fast tracking can result in lengthening the project schedule.
(True/False)
4.8/5
(75)
The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.
(Multiple Choice)
4.8/5
(82)
A disadvantage of using Gantt charts is that they do not provide a standard format for displaying planned project schedule information.
(True/False)
4.9/5
(80)
A draft schedule for a project is most likely to be found in a _____.
(Multiple Choice)
4.8/5
(73)
The _____ for an activity is the latest possible time an activity might begin without delaying the project finish date.
(Multiple Choice)
5.0/5
(78)
The _____ is based on the fact that any complex system at any point in time often has only one aspect or constraint that limits its ability to achieve more of its goal.
(Short Answer)
4.8/5
(74)
A drawback of using _____ or sample files is that managers and their teams might rely heavily on them and ignore unique concerns for their particular projects.
(Short Answer)
4.8/5
(80)
In project time management, which of the following processes primarily involve identifying and documenting the relationships between project activities?
(Multiple Choice)
4.9/5
(67)
The _____ is a tabulation of activities to be included on a project schedule.
(Short Answer)
4.7/5
(80)
One of PERT's main disadvantages is that it does not address the risk associated with duration estimates.
(True/False)
4.9/5
(70)
Describe critical path analysis. How is the critical path calculated?
(Essay)
4.9/5
(77)
Showing 1 - 20 of 102
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)