Exam 5: Quality and Performance
Exam 1: Using Operations to Compete107 Questions
Exam 2: Project Management151 Questions
Exam 3: Process Strategy149 Questions
Exam 4: Process Analysis192 Questions
Exam 5: Quality and Performance223 Questions
Exam 6: Capacity Planning133 Questions
Exam 7: Constraint Management160 Questions
Exam 8: Lean Systems179 Questions
Exam 9: Supply Chain Inventory Management216 Questions
Exam 10: Supply Chain Design93 Questions
Exam 11: Supply Chain Location Decisions126 Questions
Exam 12: Supply Chain Integration130 Questions
Exam 13: Supply Chain Sustainability and Humanitarian Logistics77 Questions
Exam 14: Forecasting183 Questions
Exam 15: Operations Planning and Scheduling191 Questions
Exam 16: Resource Planning149 Questions
Exam 17: Decision Making118 Questions
Exam 18: Waiting Line127 Questions
Exam 19: Special Inventory Models53 Questions
Exam 20: Linear Programming84 Questions
Exam 21: Simulation61 Questions
Exam 22: Financial Analysis60 Questions
Exam 23: Acceptance Sampling Plans88 Questions
Exam 24: Measuring Output Rates103 Questions
Exam 25: Learning Curve Analysis56 Questions
Exam 26: Operations Scheduling131 Questions
Select questions type
A company is interested in monitoring the average time it takes to serve its customers.An appropriate control chart would be:
(Multiple Choice)
4.8/5
(84)
A process is monitored with a control chart.The process is correctly judged to be in-control once the results from the most recent sample are plotted.Therefore,all of the output produced at that time is good.
(True/False)
5.0/5
(87)
Explain the difference between the Baldrige Performance Excellence Program and ISO 9001:2008.
(Essay)
4.8/5
(84)
A hotel tracks the number of complaints per month.When the process is in control,there is an average of 35 complaints per month.Assume that a 2-sigma control limit is used.What is the upper control limit?
(Multiple Choice)
4.9/5
(77)
Which step of the Six Sigma DMAIC procedure monitors the process to make sure high performance levels are maintained?
(Multiple Choice)
4.9/5
(81)
A company is interested in monitoring the variability in the weight of the fertilizer bags it produces.An appropriate control chart would be:
(Multiple Choice)
4.8/5
(83)
Statistical process control (SPC)is the application of statistical techniques to determine whether a quantity of material should be accepted or rejected.
(True/False)
4.8/5
(82)
Table 5.3
-Use the information from Table 5.3.What is the upper control limit (UCL)if the bank were to use z = 2 and a sample size of 100?
(Multiple Choice)
4.7/5
(71)
Why is employee empowerment important in a total quality management program?
(Essay)
4.8/5
(77)
A manufacturer embarking on a Six Sigma program sets the goal of having true Six Sigma capability for all processes by the end of the month.If their current process capability index on a key metric is less than 2.0 and the process capability ratio is 1.5,what must happen with the process standard deviation?
(Multiple Choice)
4.9/5
(75)
A sampling plan is best for evaluating quality when: (1)Inspection costs are high
(2)Inspection costs are low
(3)Non-destructive testing is available
(4)Destructive testing is required
(Multiple Choice)
4.9/5
(83)
Which alternative will increase the probability of detecting a shift in the process average?
(Multiple Choice)
4.9/5
(71)
Historically,the average proportion of defective bars has been 0.015.Samples will be of 100 bars each.Construct a p-chart using z = 3.Suppose a sample had 0.04 defectives.What would you do?
(Multiple Choice)
4.8/5
(88)
A firm that has embraced the notion of quality at the source is more likely to have:
(Multiple Choice)
4.9/5
(88)
If an x-bar chart is constructed using the data in Table 5.4,what conclusion can be reached?
(Multiple Choice)
4.7/5
(77)
A metal-cutting operation has a target value of 20 and consistently averages 19.8 with a standard deviation of 0.5.The design engineers have established an upper specification limit of 22 and a lower specification limit of 18.What is the process capability index?
(Multiple Choice)
4.8/5
(81)
When considering the plan-do-study-act cycle for problem solving,instructing other employees in the use of the new process occurs in the ________ step.
(Multiple Choice)
4.7/5
(84)
Historically,the average time to service a customer complaint has been 3 days and the standard deviation has been 0.50 day.Management would like to specify the control limits for an
chart with a sample size of 10- and 3- sigma limits.Suppose the next sample of 10 yielded the following result: 3.2,2.1,3.6,2.8,3.9,3.5,2.7,4.1,2.6,and 3.3.What conclusion can be drawn?
(Multiple Choice)
4.8/5
(88)
Showing 181 - 200 of 223