Exam 8: Lean Systems

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Mixed-model assembly is a type of assembly that produces a mix of models in smaller lots.

(True/False)
4.8/5
(72)

Weeding out unnecessary items,neatly arranging what's left,and cleaning the work area are components of:

(Multiple Choice)
4.8/5
(76)

The production of 150 units during a 480-minute work shift results in a takt time of:

(Multiple Choice)
4.8/5
(82)

A plant's manufacturing process has a takt time of 90 seconds per unit.This results in a process output of how many units per hour?

(Essay)
4.9/5
(77)

Which of the following actions would decrease the number of containers in use in a Kanban system?

(Multiple Choice)
4.8/5
(83)

Automatically stopping the process when something is wrong and then fixing the problems on the line itself as they occur is called jidoka.

(True/False)
4.8/5
(78)

The ________ method activates production of a service or item based on customer demand.

(Essay)
4.8/5
(83)

Using expensive,high precision equipment,even when simpler machines would suffice,is encouraged when lean systems are implemented,because this is the only way high quality manufacturing can be achieved.

(True/False)
4.9/5
(62)

Lean systems do not need stable master production schedules.

(True/False)
4.9/5
(70)

Options for achieving line-flow layouts in a lean system include assigning one worker to operate several different machines in a line and creating cells to produce similar product groups called families.

(True/False)
4.9/5
(82)

Briefly outline the steps to be followed in evaluating and improving a process using value stream mapping.

(Essay)
4.9/5
(74)

What are some of the approaches used to achieve the high quality levels associated with lean systems?

(Essay)
5.0/5
(67)

Automatically stopping the process when something is wrong and then fixing the problems on the line itself as they occur is called heijunka.

(True/False)
4.9/5
(82)

Manufacturing an item before it is needed in a lean system is not considered waste,because it helps keep material flowing through the system.

(True/False)
4.8/5
(90)

Often in value stream mapping,analysts must rely on process information from shop floor workers rather than direct observation in an effort to quickly develop a work plan and accelerate implementing the improved process.

(True/False)
5.0/5
(89)

Long production runs,poor material flows,and processes that are not tightly linked to one another can cause over 90% of a product's lead time to be spent waiting.

(True/False)
4.9/5
(68)

To complete the current state drawing of a process,a map of the current situation is developed,including such items as material and information flows,process times,setup times,batch sizes,scrap rates,and number of people required.

(True/False)
4.8/5
(63)

The final assembly schedule in a lean system:

(Multiple Choice)
4.8/5
(78)

Just-in-time (JIT)systems rely on inspectors to inspect quality into the product.

(True/False)
4.8/5
(67)

When implementing a lean system:

(Multiple Choice)
4.8/5
(82)
Showing 41 - 60 of 179