    Manufacturing an Item Before It Is Needed in a Lean
Solved

Manufacturing an Item Before It Is Needed in a Lean

Question 54

Question 54

True/False

Manufacturing an item before it is needed in a lean system is not considered waste,because it helps keep material flowing through the system.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q33: Often in value stream mapping, analysts must

Q38: To complete the current state drawing of

Q39: Long production runs, poor material flows, and

Q41: Lean systems do not need stable master

Q43: The final assembly schedule in a lean

Q53: Automatically stopping the process when something is

Q71: Briefly outline the steps to be followed

Q93: Just-in-time (JIT) systems rely on inspectors to

Q96: Options for achieving line-flow layouts in a

Q102: What are some of the approaches used

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2026) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines