Exam 3: Project Management
Exam 1: Introduction to the Field59 Questions
Exam 2: Operations and Supply Strategy61 Questions
Exam 3: Project Management95 Questions
Exam 4: Product and Service Design53 Questions
Exam 5: Strategic Capacity Management52 Questions
Exam 6: Process Analysis50 Questions
Exam 7: Manufacturing Processes42 Questions
Exam 8: Service Processes59 Questions
Exam 9: Six Sigma Quality83 Questions
Exam 10: Supply-Chain Strategy67 Questions
Exam 11: Logistics and Facility Location56 Questions
Exam 12: Lean Manufacturing74 Questions
Exam 13: Operations Consulting Reengineering68 Questions
Exam 14: Enterprise Resource Planning Systems35 Questions
Exam 15: Demand Management and Forecasting105 Questions
Exam 16: Aggregate Sales and Operations Planning64 Questions
Exam 17: Inventory Control100 Questions
Exam 18: Material Requirements Planning111 Questions
Exam 19: Scheduling69 Questions
Exam 20: Constraint Management64 Questions
Exam 21: Linear Programming Using the Excel Solver40 Questions
Exam 22: Learning Curves57 Questions
Exam 23: Job Design Work Measurement61 Questions
Exam 24: Waiting Line Analysis61 Questions
Exam 25: Process Capability and Spc75 Questions
Exam 26: Simulation54 Questions
Select questions type
In CPM the late start time estimate is the latest time you can start an activity and still keep the entire project on schedule.
(True/False)
4.9/5
(81)
A simple project listing of five activities,their predecessors and their respective time estimates are presented below: Activity Immediate Predecessor Time in Days A None 2 B A 2 C A 1 D B and C 3 E D 1
Using the Single Time Estimate CPM procedure,which activities have slack in this project?
(Multiple Choice)
4.8/5
(79)
If the pessimistic duration of an activity is 24,the most likely duration is 15 and the optimistic duration is 6,what is the variance for the activity time when using CPM analysis?
(Short Answer)
4.8/5
(82)
One of the assumptions of CPM is that project activity times can be estimated accurately.
(True/False)
4.8/5
(60)
We assume in CPM analysis that the activity times are independent and therefore the sum of the variances of the activities along the critical path is the variance of the expected time to complete the path.
(True/False)
4.9/5
(90)
Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs. Immediate Normal Crash Normal Crash Activity Predecessor Time Time Cost Cost A None 3 2 \ 200 \ 400 B A 4 3 \ 300 \ 600 C A 1 1 \ 300 \ 300 D B and C 3 2 \ 500 \ 550 E D 2 1 \ 500 \ 900
If you crash this project to reduce the total time by four days,what is the total time of the project and total cost?
(Multiple Choice)
4.9/5
(77)
Some of the advantages of a functional project where the project is housed in a functional division include which of the following?
(Multiple Choice)
4.8/5
(73)
A company must perform a maintenance project consisting of seven activities.The activities,their predecessors and their respective time estimates are presented below: Immediate Activity Designation Predecessor Time in Days Break down both machines A None 3 Clean machine 1 B A 3 Clean machine 2 C A 3 Re-set machine 1 D B 4 Re-set machine 2 E C 2 Re-calibrate both machines F D and E 1 Final test G F 1
Using the Single Time Estimate CPM procedure,which activities have slack in this project?
(Multiple Choice)
4.8/5
(67)
In a Gantt chart the horizontal axis is usually which of the following?
(Multiple Choice)
4.8/5
(90)
You ask your subordinates how long it will take to complete the job they are working on.The subordinates say,"If everything goes right it will take 6 hours,most likely it will take 8 hours and if everything goes wrong it will take until the end of tomorrow or another 16 hours".Since this job is a part of a larger project you must estimate the expected time it will take to complete the job.Using the three activity time estimation procedure for CPM,what is the expected time for this job?
(Multiple Choice)
4.8/5
(82)
Calculating the early start and early finish times for each activity in a CPM analysis does not provide any useful information.
(True/False)
4.9/5
(73)
A matrix project structure may be referred to as a "skunk works".
(True/False)
4.8/5
(79)
One of the disadvantages of a pure project organizational structure is that the project manager has full authority over the project.
(True/False)
4.8/5
(85)
The critical path in a CPM analysis is found by locating the activities times with zero slack.
(True/False)
5.0/5
(66)
If you have an optimistic time of 4 weeks,a most likely time of 6 weeks and a pessimistic time of 8 weeks on an activity in a CPM managed project,what is the expected time for this activity?