Exam 3: Project Management
Exam 1: Introduction to the Field59 Questions
Exam 2: Operations and Supply Strategy61 Questions
Exam 3: Project Management95 Questions
Exam 4: Product and Service Design53 Questions
Exam 5: Strategic Capacity Management52 Questions
Exam 6: Process Analysis50 Questions
Exam 7: Manufacturing Processes42 Questions
Exam 8: Service Processes59 Questions
Exam 9: Six Sigma Quality83 Questions
Exam 10: Supply-Chain Strategy67 Questions
Exam 11: Logistics and Facility Location56 Questions
Exam 12: Lean Manufacturing74 Questions
Exam 13: Operations Consulting Reengineering68 Questions
Exam 14: Enterprise Resource Planning Systems35 Questions
Exam 15: Demand Management and Forecasting105 Questions
Exam 16: Aggregate Sales and Operations Planning64 Questions
Exam 17: Inventory Control100 Questions
Exam 18: Material Requirements Planning111 Questions
Exam 19: Scheduling69 Questions
Exam 20: Constraint Management64 Questions
Exam 21: Linear Programming Using the Excel Solver40 Questions
Exam 22: Learning Curves57 Questions
Exam 23: Job Design Work Measurement61 Questions
Exam 24: Waiting Line Analysis61 Questions
Exam 25: Process Capability and Spc75 Questions
Exam 26: Simulation54 Questions
Select questions type
Which of the following is a reason that project management is important?
(Multiple Choice)
4.9/5
(74)
Which of the following is an assumption made in using CPM analysis?
(Multiple Choice)
4.8/5
(80)
In CPM analysis it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following?
(Multiple Choice)
4.8/5
(85)
One of the advantages of a functional project organizational structure is that a team member can work on several projects.
(True/False)
4.9/5
(77)
You have the following time and cost information below for use in a Time-Cost CPM Scheduling model. Activity Normal Time Crash Time Normal Cost Crash Cost A 3 2 \ 400 \ 600 B 5 3 \ 600 \ 1200 C 4 1 \ 300 \ 1500
What are the three costs per unit of time to expedite each activity?
(Multiple Choice)
4.8/5
(83)
If the pessimistic duration of an activity is 24,the most likely duration is 15 and the optimistic duration is 6,what is the variance for the activity time when using CPM analysis?
(Multiple Choice)
4.8/5
(74)
Upper level management must decide between pure,functional and matrix structures as ways to organize projects.
(True/False)
4.8/5
(86)
The "Z" distribution used to calculate the probability of completing a project on time is only useful in calculating probabilities where the desired time is greater than the expected time.
(True/False)
4.8/5
(82)
A matrix project attempts to blend properties of functional and pure project structures.
(True/False)
4.8/5
(73)
Complex projects are often subdivided into a series of tasks that are typically configured to be not longer than several months in duration.
(True/False)
4.9/5
(72)
A work breakdown structure is used in project management but not in the critical path method.
(True/False)
4.9/5
(82)
You have just been assigned to oversee a series of projects.Functional areas will loan you personnel for each project and separate project managers will be responsible for separate projects.These project managers will report to you.Which project management structure is being used?
(Multiple Choice)
4.9/5
(51)
You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below.
(Essay)
4.9/5
(75)
You are managing a project and need to cut the cost of the project.You decide to transfer workers to another job to cut the project's costs.Costs associated with transferring the workers are an example of project indirect costs.
(True/False)
4.9/5
(78)
Showing 41 - 60 of 95
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)