The Gantt chart is an example of a project control chart.

(True/False)
4.7/5
(81)

Which of the following is a reason that project management is important?

(Multiple Choice)
4.9/5
(74)

An event is a subdivision of a project.

(True/False)
4.8/5
(75)

A project starts out as which of the following?

(Multiple Choice)
4.9/5
(91)

Which of the following is an assumption made in using CPM analysis?

(Multiple Choice)
4.8/5
(80)

In CPM analysis it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following?

(Multiple Choice)
4.8/5
(85)

One of the advantages of a functional project organizational structure is that a team member can work on several projects.

(True/False)
4.9/5
(77)

CPM is an abbreviation for Critical Path Method.

(True/False)
4.9/5
(84)

You have the following time and cost information below for use in a Time-Cost CPM Scheduling model. Activity Normal Time Crash Time Normal Cost Crash Cost A 3 2 \ 400 \ 600 B 5 3 \ 600 \ 1200 C 4 1 \ 300 \ 1500 What are the three costs per unit of time to expedite each activity?

(Multiple Choice)
4.8/5
(83)

If the pessimistic duration of an activity is 24,the most likely duration is 15 and the optimistic duration is 6,what is the variance for the activity time when using CPM analysis?

(Multiple Choice)
4.8/5
(74)

In the Time-Cost CPM model,cost is a linear function of time.

(True/False)
4.9/5
(88)

Upper level management must decide between pure,functional and matrix structures as ways to organize projects.

(True/False)
4.8/5
(86)

The "Z" distribution used to calculate the probability of completing a project on time is only useful in calculating probabilities where the desired time is greater than the expected time.

(True/False)
4.8/5
(82)

A matrix project attempts to blend properties of functional and pure project structures.

(True/False)
4.8/5
(73)

Complex projects are often subdivided into a series of tasks that are typically configured to be not longer than several months in duration.

(True/False)
4.9/5
(72)

A work breakdown structure is used in project management but not in the critical path method.

(True/False)
4.9/5
(82)

You have just been assigned to oversee a series of projects.Functional areas will loan you personnel for each project and separate project managers will be responsible for separate projects.These project managers will report to you.Which project management structure is being used?

(Multiple Choice)
4.9/5
(51)

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below.

(Essay)
4.9/5
(75)

You are managing a project and need to cut the cost of the project.You decide to transfer workers to another job to cut the project's costs.Costs associated with transferring the workers are an example of project indirect costs.

(True/False)
4.9/5
(78)

What are "project milestones"?

(Essay)
5.0/5
(92)