Exam 3: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

For an activity in a Single Time Estimate CPM analysis,the Early Finish time is 8 and the Late Finish time is 10.Which of the following statements is true?

(Multiple Choice)
4.7/5
(75)

The project indirect costs associated with a project include overhead,facilities and resource opportunity costs.

(True/False)
4.9/5
(71)

In a CPM analysis if you subtract the late finish from the early finish the result is the activity's slack time.

(True/False)
4.8/5
(80)

The critical path in a CPM analysis is always the shortest path through the network.

(True/False)
4.7/5
(79)

In calculating the probabilities in a CPM analysis the desired time is determined by calculating the expected time for the project as a whole.

(True/False)
4.9/5
(78)

One of the assumptions made using CPM is that project activities can be identified with clear beginning and ending points.

(True/False)
4.8/5
(76)

A company must perform a maintenance project consisting of seven activities.The activities,their predecessors and their respective time estimates are presented below: Immediate Activity Designation Predecessor Time in Days Break down both machines A None 3 Clean machine 1 B A 3 Clean machine 2 C A 3 Re-set machine 1 D B 1 Re-set machine 2 E C 2 Re-calibrate both machines F D and E 1 Final test G F 2 Using the Single Time Estimate CPM procedure,what is the Latest Finish Time for the last activity in this project (i.e. ,the total time to complete the project)?

(Multiple Choice)
4.9/5
(93)

For an activity in a Single Time Estimate CPM analysis the Early Finish time is 20 and the Late Finish time is 20.Which of the following statements is true?

(Multiple Choice)
4.7/5
(92)

The fact that organizations are flattening is one reason that projects are more crucial and project management is important as a way to get things done.

(True/False)
4.8/5
(76)

You have been placed in charge of a large project.Shortened communication lines are required to insure quick resolution of problems as they arise.You recognize that the project is going to take a lot of time and require a lot of team pride,motivation and commitment by all members.Which project management structure should you use in this situation?

(Multiple Choice)
4.9/5
(74)

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below. Immediate Normal Crash Normal Crash Activity Immediate Time Time Cost (Direct) Cost (Direct) A None 3 2 \ 300 \ 400 B A 3 3 \ 100 \ 100 C A 1 1 \ 200 \ 200 D B and C 3 2 \ 400 \ 550 E D 2 1 \ 500 \ 900 F E 3 3 \ 200 \ 200 G F 2 2 \ 100 \ 100 The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400,15 days they will be $250,14 days they will be $200 and 13 days they will be $100.At what day do we achieve the lowest total project cost (i.e. ,direct plus indirect costs)?

(Multiple Choice)
4.9/5
(80)

If you have an optimistic time of 4 weeks,a most likely time of 6 weeks and a pessimistic time of 14 weeks on an activity in a CPM managed project,what is the expected time for this activity?

(Multiple Choice)
4.9/5
(71)

The critical path in a project is that sequence of activities that consume the longest amount of time in a project network of activities.

(True/False)
4.8/5
(71)

A listing of immediate predecessor activities is important information in a single time estimate CPM analysis for which of the following reasons?

(Multiple Choice)
5.0/5
(77)

If the pessimistic duration of an activity is 10 and the optimistic duration is 4,what is the variance for the activity time when using CPM analysis?

(Multiple Choice)
4.7/5
(81)

A simple project listing of five activities and their respective time estimates are presented below: Activity Immediate Predecessor Time in Days A None 1 B A 2 C A 1 D B and C 3 E D 2 Using the Single Time Estimate CPM procedure,which activities make up the critical path?

(Multiple Choice)
4.8/5
(88)

Derivative projects are those which address incremental changes to products or processes.

(True/False)
4.8/5
(70)

You have just computed a Z=2.55 in a CPM analysis of a critical path for a project.Based on this Z value what is the probability of completing this project on time?

(Multiple Choice)
4.9/5
(87)

If each activity time is known with certainty in a CPM analysis,which of the following methodologies can be used to analyze the project?

(Multiple Choice)
4.9/5
(81)

Using the Time-Cost CPM model,the crash time is the shortest possible time allowed for each activity in the project.

(True/False)
4.7/5
(71)
Showing 61 - 80 of 95
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)