Exam 12: Lean Manufacturing

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

JIT is typically applied to non-repetitive manufacturing.

Free
(True/False)
4.9/5
(83)
Correct Answer:
Verified

False

In setting up a kanban control system you need to determine the number of kanban card sets needed.If the expected demand during lead time is 24 per hour,safety stock is 10% of the demand during lead time,the container size is 5.If the lead time to replenish an order is 5 hours,what number of kanban card sets is needed?

Free
(Short Answer)
4.9/5
(65)
Correct Answer:
Verified

27 (26.4)

Which of the following statements holds true for Kanban production control systems?

Free
(Multiple Choice)
4.8/5
(82)
Correct Answer:
Verified

B

Group technology includes the set of psychological tests and training exercises given to group workers to insure a high level of teamwork.

(True/False)
4.9/5
(70)

When implementing a lean production system a stabilized schedule is achieved using which of the following?

(Multiple Choice)
5.0/5
(79)

Lean production is a management philosophy and a pull system throughout the plant.

(True/False)
4.9/5
(72)

What are the five guidelines for implementing a lean supply chain presented by Womack and Jones,in their book Lean Thinking?

(Essay)
4.8/5
(81)

JIT manufacturing forces a firm to work with a lower water level despite safety hazards.

(True/False)
4.8/5
(83)

To implement a Kanban pull system the firm would do which of the following?

(Multiple Choice)
4.9/5
(88)

One of the many JIT techniques that have been successfully applied in service firms is leveling facility load.

(True/False)
4.8/5
(77)

JIT production means that we produce the product before it is required so the customer does not wait for the product.

(True/False)
4.8/5
(84)

In the textbook Toyota's Fujio Cho identified which of the following types of waste to be eliminated?

(Multiple Choice)
4.9/5
(73)

In setting up a Kanban control system you need to determine the number of Kanban card sets needed.If the expected demand during lead time is 25 per hour,the safety stock is 20% of the demand during lead time,the container size is 5 and the lead time to replenish an order is 5 hours,what is the number of Kanban card sets needed?

(Multiple Choice)
4.8/5
(74)

Preventive maintenance is emphasized in lean production to ensure the flows are not interrupted by downtime or malfunctioning equipment.

(True/False)
4.9/5
(76)

A focused factory network is a family of manufacturing facilities each producing components that are focused on a nearby large assembly facility.

(True/False)
4.8/5
(75)

Imagine comparing a manufacturing operation using regular lot-sizing and the same operation with a Kanban/lean production approach.What would be your expectations of the difference between the total cost (i.e. ,inventory holding costs + setup/ordering costs)of each?

(Multiple Choice)
4.8/5
(73)

Which of the following are elements that address elimination of waste under lean production?

(Multiple Choice)
4.8/5
(78)

A Kanban control system uses a signaling device to regulate JIT flows.

(True/False)
4.8/5
(70)

In Japan we would expect a focused factory to be small and have only somewhere between 30 and 1,000 workers.

(True/False)
5.0/5
(73)

A principle of value stream mapping is to concentrate on speeding up value-added operations.

(True/False)
4.8/5
(73)
Showing 1 - 20 of 74
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)