Short Answer
In setting up a kanban control system you need to determine the number of kanban card sets needed.If the expected demand during lead time is 24 per hour,safety stock is 10% of the demand during lead time,the container size is 5.If the lead time to replenish an order is 5 hours,what number of kanban card sets is needed?
Correct Answer:

Verified
Correct Answer:
Verified