Exam 18: Material Requirements Planning
Exam 1: Introduction to the Field59 Questions
Exam 2: Operations and Supply Strategy61 Questions
Exam 3: Project Management95 Questions
Exam 4: Product and Service Design53 Questions
Exam 5: Strategic Capacity Management52 Questions
Exam 6: Process Analysis50 Questions
Exam 7: Manufacturing Processes42 Questions
Exam 8: Service Processes59 Questions
Exam 9: Six Sigma Quality83 Questions
Exam 10: Supply-Chain Strategy67 Questions
Exam 11: Logistics and Facility Location56 Questions
Exam 12: Lean Manufacturing74 Questions
Exam 13: Operations Consulting Reengineering68 Questions
Exam 14: Enterprise Resource Planning Systems35 Questions
Exam 15: Demand Management and Forecasting105 Questions
Exam 16: Aggregate Sales and Operations Planning64 Questions
Exam 17: Inventory Control100 Questions
Exam 18: Material Requirements Planning111 Questions
Exam 19: Scheduling69 Questions
Exam 20: Constraint Management64 Questions
Exam 21: Linear Programming Using the Excel Solver40 Questions
Exam 22: Learning Curves57 Questions
Exam 23: Job Design Work Measurement61 Questions
Exam 24: Waiting Line Analysis61 Questions
Exam 25: Process Capability and Spc75 Questions
Exam 26: Simulation54 Questions
Select questions type
The master production schedule states the number of items to be produced during specific time periods.
(True/False)
4.8/5
(77)
One of the outputs of an MRP system is a bill of materials (BOM)file.
(True/False)
4.9/5
(84)
In a net change MRP system requirements and schedules are updated whenever a transaction is processed that has an impact on the item.
(True/False)
4.8/5
(66)
In today's modern world of rapid computing and just-in-time replenishment of supplies,freezing the master production schedule is unnecessary.
(True/False)
4.8/5
(76)
Which of the following is a dynamic lot-sizing technique that calculates the order quantity by comparing the carrying cost and the setup (or ordering)costs for various lot sizes and then selects the lot size in which these are most nearly equal?
(Multiple Choice)
4.8/5
(70)
A BOM file is often called a product structure file or product tree because it enumerates all of the component parts of the end item product.
(True/False)
4.9/5
(80)
Projected available balance is the amount of inventory that is expected as of the beginning of a period.
(True/False)
4.9/5
(86)
Under the lot-for-lot (L4L)lot sizing technique as used in MRP,we would expect which of the following?
(Multiple Choice)
4.8/5
(77)
Which of the following is considered a secondary report in an MRP system?
(Multiple Choice)
4.8/5
(85)
Use of time fences maintains a reasonably controlled flow through a production system.
(True/False)
5.0/5
(76)
MRP is most valuable in industries where a number of products are made in batches using the same productive equipment.
(True/False)
4.8/5
(92)
What is the planned-order release using an MRP program if the gross requirement is 1,600 and the inventory on hand is 600?
(Short Answer)
4.8/5
(80)
In a typical inventory status record which of the following would you not expect to see?
(Multiple Choice)
4.9/5
(83)
In a net change MRP program,a change in one item will result in a completely new inventory plan and schedule for every item in the master production schedule.
(True/False)
4.7/5
(79)
Explain why "freezing the master schedule" is not the same as reducing the Level of service to customers.
(Essay)
4.8/5
(85)
The least unit cost method (LUC)of lot-sizing technique adds ordering and inventory carrying cost for each trial lot size and divides by the number of units in each lot size,picking the lot size with the lowest unit cost.
(True/False)
4.8/5
(78)
Showing 81 - 100 of 111