Which of the Following Is Considered a Secondary Report in an MRP

Question 89

Multiple Choice

Which of the following is considered a secondary report in an MRP system?


A) Planned order schedule
B) Performance reports
C) Inventory record
D) Firm orders from known customers
E) Engineering change reports