Exam 4: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Some of the advantages of a functional project where the project is housed in a functional division include which of the following?

(Multiple Choice)
4.7/5
(74)

Upper-level management must decide between pure, functional, and matrix structures as ways to organize projects.

(True/False)
4.8/5
(77)

The valuations in an earned value management analysis must be either profits or revenue.

(True/False)
4.9/5
(84)

Using the time-cost CPM model, the crash time is the shortest possible time allowed for each activity in the project.

(True/False)
4.9/5
(82)

The critical path in a project is that sequence of activities that consume the longest amount of time in a project network of activities.

(True/False)
4.8/5
(72)

A simple project listing of five activities and their respective time estimates are presented here: A simple project listing of five activities and their respective time estimates are presented here:   Using CPM, which activities make up the critical path? Using CPM, which activities make up the critical path?

(Multiple Choice)
4.9/5
(72)

The project indirect costs associated with a project include overhead, facilities, and resource opportunity costs.

(True/False)
4.8/5
(89)

A matrix project structure is often referred to as a "skunkworks."

(True/False)
4.9/5
(77)

Project management software available today combines CPM and other scheduling aids, like Gantt charting, to aid in tracking progress of project completion.

(True/False)
4.9/5
(83)

One of the assumptions made using CPM is that project activities can be identified with clear beginning and ending points.

(True/False)
4.9/5
(77)

In a Gantt chart, the horizontal axis is usually which of the following?

(Multiple Choice)
4.7/5
(75)

A simple project listing of five activities, their predecessors, and their respective time estimates are presented here: A simple project listing of five activities, their predecessors, and their respective time estimates are presented here:   Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)? Using CPM, what is the latest finish time for the last activity in this project (i.e., the total time to complete the project)?

(Multiple Choice)
4.8/5
(75)

Describe how CPM handles the trade-offs between time and cost in the scheduling of a project.

(Essay)
4.8/5
(93)

A matrix project attempts to blend properties of functional and pure project structures.

(True/False)
4.8/5
(82)

You have collected the data for a time-cost CPM scheduling model analysis.The time is in days and the project "direct costs" are given here. You have collected the data for a time-cost CPM scheduling model analysis.The time is in days and the project direct costs are given here.   The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs)? The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs)?

(Multiple Choice)
4.9/5
(78)

You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values.What can you conclude?

(Multiple Choice)
4.8/5
(78)

PERT is an abbreviation for which of the following methodologies?

(Multiple Choice)
4.8/5
(90)

A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented here: A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented here:   Using CPM, which activities make up the critical path? Using CPM, which activities make up the critical path?

(Multiple Choice)
4.8/5
(70)

You have the following time and cost information for use in a time-cost CPM scheduling model. You have the following time and cost information for use in a time-cost CPM scheduling model.   What are the three costs per unit of time to expedite each activity? What are the three costs per unit of time to expedite each activity?

(Multiple Choice)
4.8/5
(78)

An advantage of a pure project where self-contained teams work full time on a project is which of the following?

(Multiple Choice)
4.9/5
(84)
Showing 21 - 40 of 78
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)