Exam 22: Workcenter Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A material requirements planning system is an example of which of the following scheduling systems?

(Multiple Choice)
4.8/5
(57)

The objective of Johnson's rule for job sequencing is to minimize flow time from the beginning of the first job until the completion of the last job.

(True/False)
4.9/5
(76)

The textbook underscores the importance of scheduling with the phrase "workflow equals cash flow, and scheduling lies at the heart of the process."

(True/False)
4.7/5
(74)

Priority rules are the rules used to obtain a job sequence in production scheduling.

(True/False)
4.8/5
(78)

Shop-floor control (or production activity control) can involve reviewing the status and controlling the progress of orders as they are being worked on.

(True/False)
4.8/5
(85)

A job has 10 days of processing time left to do before completion, and today is the 5th day of the month.If the job is due on the 15th day of the month, what is its critical ratio?

(Multiple Choice)
4.9/5
(69)

What is sub-optimization in scheduling? ______________________________________________.

(Essay)
4.8/5
(84)

Which of the following might be a status and exception report used in shop-floor control?

(Multiple Choice)
4.9/5
(76)

Which of the following is a tool of shop-floor control?

(Multiple Choice)
5.0/5
(80)

One of the principles of work center scheduling is that, while certainty of standards, routings, and so forth is not entirely possible in a shop, certainty should always be an objective to work toward.

(True/False)
4.8/5
(84)

Assume you are sequencing jobs using Johnson's rule.A particular job requires 7 hours to assemble and then is followed by 8 hours in the painting department.Which of the following is where you would schedule this job?

(Multiple Choice)
4.9/5
(89)

A shop-floor control system is a system that uses data from the shop floor as well as data processing files to maintain and communicate status information on shop orders and work centers.

(True/False)
4.8/5
(73)

Which of the following is not an objective of work center scheduling?

(Multiple Choice)
4.8/5
(62)

A system that "backward schedules" is designed to determine and report the earliest date an order can be completed.

(True/False)
4.9/5
(81)

Assume you are sequencing jobs using Johnson's rule.A particular job requires 3 hours to assemble and then is followed by 2 hours in the painting department.Which of the following is where you would schedule this job?

(Multiple Choice)
4.9/5
(74)

One of the principles of work center scheduling is that the effectiveness of any shop should be measured by speed of flow through the shop.

(True/False)
4.8/5
(93)

Which of the following is a priority rule used to schedule the sequence of jobs in a production operation?

(Multiple Choice)
4.9/5
(79)

For a low-volume job shop type of manufacturing, which of the following is the typical production scheduling approach?

(Multiple Choice)
4.8/5
(99)

A work center has five jobs assigned to it.They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D, and E.The work center may work on only one job at a time and must complete any job it starts before starting another job.Job A has a processing time of 6 days and is due to the customer in 9 days.Job B has a processing time of 2 days and is due in 16 days.Job C has a processing time of 4 days and is due in 10 days.Job D has a processing time of 3 days and is due in 7 days.Job E has a processing time of 5 days and is due in 12 days.Using the slack time remaining priority rule, in what order should these jobs be undertaken? _______________________________________.

(Short Answer)
4.9/5
(92)

A work center has five jobs assigned to it.They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D, and E.The work center may work on only one job at a time and must complete any job it starts before starting another job.Job A has a processing time of 6 days and is due to the customer in 9 days.Job B has a processing time of 2 days and is due in 16 days.Job C has a processing time of 4 days and is due in 10 days.Job D has a processing time of 3 days and is due in 7 days.Job E has a processing time of 5 days and is due in 12 days.Using the shortest operating time priority rule, what will be the average lateness of these orders? ______________________________________.

(Short Answer)
4.9/5
(83)
Showing 21 - 40 of 72