Exam 25: Budgetary Control and Responsibility Accounting
Exam 1: Accounting in Action220 Questions
Exam 2: The Recording Process192 Questions
Exam 3: Adjusting the Accounts216 Questions
Exam 4: Completing the Accounting Cycle203 Questions
Exam 5: Accounting for Merchandising Operations221 Questions
Exam 6: Inventories204 Questions
Exam 7: Accounting Information Systems139 Questions
Exam 8: Fraud, Internal Control, and Cash212 Questions
Exam 9: Accounting for Receivables220 Questions
Exam 10: Plant Assets, Natural Resources, and Intangible Assets293 Questions
Exam 11: Current Liabilities and Payroll Accounting207 Questions
Exam 12: Accounting for Partnerships210 Questions
Exam 13: Corporations: Organization and Capital Stock Transactions195 Questions
Exam 14: Corporations: Dividends, Retained Earnings, and Income Reporting176 Questions
Exam 15: Long-Term Liabilities215 Questions
Exam 16: Investments178 Questions
Exam 17: Statement of Cash Flows203 Questions
Exam 18: Financial Analysis: the Big Picture225 Questions
Exam 19: Managerial Accounting197 Questions
Exam 20: Job Order Costing199 Questions
Exam 21: Process Costing198 Questions
Exam 22: Cost-Volume-Profit217 Questions
Exam 23: Incremental Analysis208 Questions
Exam 24: Budgetary Planning207 Questions
Exam 25: Budgetary Control and Responsibility Accounting207 Questions
Exam 26: Standard Costs and Balanced Scorecard221 Questions
Select questions type
Variance analysis facilitates the principle of "management by exception."
(True/False)
4.8/5
(68)
Loomis Company uses both standards and budgets. The company estimates that production for the year will be 250,000 units of Product Fast. To produce these units of Product Fast, the company expects to spend $600,000 for materials and $800,000 for labor.
Instructions
Compute the estimates for (a) a standard cost and (b) a budgeted cost.
(Essay)
4.7/5
(85)
A direct labor price standard is frequently called the direct labor efficiency standard.
(True/False)
4.9/5
(76)
Fugate Company planned to use 1 yard of plastic per unit budgeted at $81 a yard. However, the plastic actually cost $80 per yard. The company actually made 2,600 units, although it had planned to make only 2,200 units. Total yards used for production were 2,640. How much is the total materials variance?
(Multiple Choice)
4.8/5
(76)
Standard cost + price variance + quantity variance = Budgeted cost.
(True/False)
4.8/5
(85)
Keller Company has a materials price standard of $2.00 per pound. Five thousand pounds of materials were purchased at $2.20 a pound. The actual quantity of materials used was 5,000 pounds, although the standard quantity allowed for the output was 4,500 pounds.
Keller Company's total materials variance is
(Multiple Choice)
4.8/5
(69)
A company developed the following per unit materials standards for its product: 3 pounds of direct materials at $4 per pound. If 12,000 units of product were produced last month and 37,500 pounds of direct materials were used, the direct materials quantity variance was
(Multiple Choice)
4.8/5
(67)
ToolTime has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2,000 units, ToolTime used 3,850 hours of labor at a total cost of $46,970. ToolTime's labor quantity variance is
(Multiple Choice)
5.0/5
(67)
ToolTime has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2,000 units, ToolTime used 3,850 hours of labor at a total cost of $46,970. ToolTime's total labor variance is
(Multiple Choice)
4.8/5
(89)
A debit to the Overhead Volume Variance account indicates that the standard hours allowed for the output produced was greater than the standard hours at normal capacity.
(True/False)
4.9/5
(82)
ToolTime has a standard of 1.5 pounds of materials per unit, at $4 per pound. In producing 2,000 units, ToolTime used 3,100 pounds of materials at a total cost of $12,090. ToolTime's materials price variance is
(Multiple Choice)
4.9/5
(94)
The per-unit standards for direct materials are 2 pounds at $4 per pound. Last month, 11,200 pounds of direct materials that actually cost $42,400 were used to produce 6,000 units of product. The direct materials quantity variance for last month was
(Multiple Choice)
4.9/5
(82)
The following information was taken from the annual manufacturing overhead cost budget of Coen Company.
During the year, 5,600 units were produced, 18,340 hours were worked, and the actual manufacturing overhead was $75,600. Actual fixed manufacturing overhead costs equaled budgeted fixed manufacturing overhead costs. Overhead is applied on the basis of direct labor hours. Coen's total overhead variance is
(Multiple Choice)
4.9/5
(66)
The per-unit standards for direct labor are 2 direct labor hours at $15 per hour. If in producing 1,200 units, the actual direct labor cost was $32,000 for 2,000 direct labor hours worked, the total direct labor variance is
(Multiple Choice)
4.9/5
(87)
A ________________ is expressed as a unit amount, whereas a _________________ is expressed as a total amount.
(Short Answer)
4.8/5
(102)
The direct materials price standard should include an amount for all of the following except
(Multiple Choice)
4.8/5
(68)
An unfavorable labor quantity variance indicates that the actual number of direct labor hours worked was greater than the number of direct labor hours that should have been worked for the output attained.
(True/False)
4.9/5
(73)
Inventories cannot be valued at standard cost in financial statements.
(True/False)
4.8/5
(83)
Colt Widgets prepared its income statement for management using a standard cost accounting system. Which of the following appears at the "standard" amount?