Exam 25: Budgetary Control and Responsibility Accounting
Exam 1: Accounting in Action220 Questions
Exam 2: The Recording Process192 Questions
Exam 3: Adjusting the Accounts216 Questions
Exam 4: Completing the Accounting Cycle203 Questions
Exam 5: Accounting for Merchandising Operations221 Questions
Exam 6: Inventories204 Questions
Exam 7: Accounting Information Systems139 Questions
Exam 8: Fraud, Internal Control, and Cash212 Questions
Exam 9: Accounting for Receivables220 Questions
Exam 10: Plant Assets, Natural Resources, and Intangible Assets293 Questions
Exam 11: Current Liabilities and Payroll Accounting207 Questions
Exam 12: Accounting for Partnerships210 Questions
Exam 13: Corporations: Organization and Capital Stock Transactions195 Questions
Exam 14: Corporations: Dividends, Retained Earnings, and Income Reporting176 Questions
Exam 15: Long-Term Liabilities215 Questions
Exam 16: Investments178 Questions
Exam 17: Statement of Cash Flows203 Questions
Exam 18: Financial Analysis: the Big Picture225 Questions
Exam 19: Managerial Accounting197 Questions
Exam 20: Job Order Costing199 Questions
Exam 21: Process Costing198 Questions
Exam 22: Cost-Volume-Profit217 Questions
Exam 23: Incremental Analysis208 Questions
Exam 24: Budgetary Planning207 Questions
Exam 25: Budgetary Control and Responsibility Accounting207 Questions
Exam 26: Standard Costs and Balanced Scorecard221 Questions
Select questions type
Ratliff Industries provided the following information about its standard costing system for 2011:
Instructions
Determine the amount of the materials price variance. By how much will the materials price variances differ if the price variance is determined at the time of production?
Free
(Essay)
4.9/5
(73)
Correct Answer:
Identification of price variances at the time of purchase:
Materials price variance = (Actual quantity purchased × Actual price) - (Actual quantity purchased x Standard price)
= (75,000 × $4.20) - (75,000 × $4) = $15,000 Unfavorable
Identification of price variances at the time of production:
Materials price variance = (Actual quantity used × Actual price) - (Actual quantity used × Standard price)
= (61,500 × $4.20) - (61,500 × $4) = $12,300 Unfavorable
Difference = $15,000 - $12,300 = $2,700 Unfavorable
George Company has a standard costing system. The following data are available for July:
a. Actual manufacturing overhead cost incurred: $22,000
b. Actual machine hours worked: 1,600
c. Overhead volume variance: $3,600 Unfavorable
d. Total overhead variance: $1,000 Unfavorable
e. Overhead is assigned to production on the basis of machine hours
Instructions
Determine the amount of (1) the controllable overhead variance and (2) the overhead applied.
Free
(Essay)
4.9/5
(78)
Correct Answer:
(1) Volume variance plus controllable variance = total overhead variance
$3,600 U + X = $1,000 U; so controllable variance = $2,600 F
(2) Overhead applied = $21,000 ($22,000 - $1,000)
A standard cost system may be used with a job order cost system but not with a process cost system.
Free
(True/False)
4.9/5
(78)
Correct Answer:
False
The following information was taken from the annual manufacturing overhead cost budget of Coen Company.
During the year, 5,600 units were produced, 18,340 hours were worked, and the actual manufacturing overhead was $75,600. Actual fixed manufacturing overhead costs equaled budgeted fixed manufacturing overhead costs. Overhead is applied on the basis of direct labor hours. Coen's volume overhead variance is
(Multiple Choice)
4.9/5
(85)
Once set, normal standards should not be changed during the year.
(True/False)
4.9/5
(74)
Setting standard costs is relatively simple because it is done entirely by accountants.
(True/False)
4.9/5
(77)
Normal standards incorporate normal contingencies of production into the standards.
(True/False)
4.7/5
(70)
Which of the following statements about overhead variances is false?
(Multiple Choice)
4.9/5
(67)
If 10,000 pounds of direct materials are purchased for $7,200 on account and the standard cost is $.70 per pound, the journal entry to record the purchase is 
(Short Answer)
4.8/5
(71)
If the labor quantity variance is unfavorable and the cause is inefficient use of direct labor, the responsibility rests with the
(Multiple Choice)
4.8/5
(71)
Budget data are not journalized in cost accounting systems with the exception of
(Multiple Choice)
4.8/5
(80)
Which one of the following describes the total overhead variance?
(Multiple Choice)
4.9/5
(84)
The difference between actual hours times the actual pay rate and actual hours times the standard pay rate is the labor _________________ variance.
(Short Answer)
5.0/5
(74)
The total overhead variance is the difference between actual overhead costs and overhead costs applied to work done.
(True/False)
4.8/5
(71)
In developing a standard cost for direct materials, a price factor and a quantity factor must be considered.
(True/False)
4.9/5
(86)
Showing 1 - 20 of 207