If customer demand exceeds process capacity, every operation with capacity utilization greater than 100 percent is an external bottleneck.

Free
(True/False)
4.8/5
(94)
Correct Answer:
Verified

True

Which of the following descriptions about waiting line models is best?

Free
(Multiple Choice)
5.0/5
(84)
Correct Answer:
Verified

A

Process Management Triangle is made up of capacity utilization, ______ and ______ .

Free
(Short Answer)
5.0/5
(73)
Correct Answer:
Verified

inventory, variability

is any stock of items used to support the production of goods and services or satisfy customer demand.

(Short Answer)
4.8/5
(75)

Capacity gap is an addition to projected demand and current capacity.

(True/False)
5.0/5
(74)

Within a process, what is a bottleneck?

(Essay)
4.9/5
(84)

Which one of the following statements about capacity expansion is best?

(Multiple Choice)
4.8/5
(80)

Innovative Inc. is experiencing a boom for the products it has introduced recently. The estimated annual sales projected for the next five years are given below. The current capacity is equivalent to only $100 million sales. The company is considering the alternative of expanding capacity to an equivalent of $250 million sales. Assume a 25 percent pretax profit margin. What is the increase in total pretax cash flow (summed over all years) that would be enjoyed because of the expansion? Year AnnualSales (in \million ) 1 100 2 140 3 170 4 200 5 250

(Multiple Choice)
4.8/5
(86)

The ______ time is the time required to change an operation from making one type of product or service to making another.

(Short Answer)
4.8/5
(74)

What information would managers use to choose the best cost- effective capacity to balance customer service with the cost of adding capacity?

(Multiple Choice)
4.8/5
(71)

The base case concept is to do nothing and simply lose orders from any demand that exceeds current capacity.

(True/False)
4.9/5
(84)

Waiting line models are often used for capacity planning.

(True/False)
4.9/5
(76)

Output measures are the usual choice for high- volume processes that produce only a limited range of similar products or services, usually expressed in terms of output over a period of time.

(True/False)
4.9/5
(80)

Which of the following is NOT a disadvantage of the wait- and- see strategy?

(Multiple Choice)
4.8/5
(76)

In an automobile service business (e.g. a muffler shop), measuring capacity based on the number of hours that the service bays will be required to satisfy expected demand is an example of an input measure of capacity.

(True/False)
4.9/5
(77)

The ______ strategy refers to a condition which involves large, infrequent jumps in capacity.

(Short Answer)
4.8/5
(103)

Which one of the following statements concerning capacity cushions is best?

(Multiple Choice)
4.9/5
(80)

According to the theory of constraints (TOC), the role of work- in- process inventory is to dictate the pace that specific items are pulled through the process.

(True/False)
4.8/5
(80)

Increasing the amount of work- in- process inventory reduces the likelihood that operations in the process will be starved.

(True/False)
5.0/5
(71)

If demand is increasing, and you also prefer to increase the time between capacity increments, then the size of increments should ______ .

(Short Answer)
4.9/5
(72)
Showing 1 - 20 of 143