Exam 12: MRP and ERP
Exam 1: Introduction to Operations Management74 Questions
Exam 2: Competitiveness, Strategy, and Productivity72 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design76 Questions
Exam 4: Extension: Reliability12 Questions
Exam 5: Strategic Capacity Planning for Products and Services106 Questions
Exam 5: Extension: Decision Theory123 Questions
Exam 6: Process Selection and Facility Layout150 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 7: Extension: Learning Curves68 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 8: Extension: The Transportation Model20 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 10: Extension: Acceptance Sampling65 Questions
Exam 11: Aggregate Planning and Master Scheduling88 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management161 Questions
Exam 14: Jit and Lean Operations87 Questions
Exam 14: Extension: Maintenance38 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming111 Questions
Select questions type
A visual depiction of the subassemblies and components that are needed to produce and/or assemble a product is called a(n):
(Multiple Choice)
4.8/5
(81)
MRP, considering inventory position, bills of material, open purchase orders, and lead times guarantees a feasible production plan if the inputs to MRP are accurate.
(True/False)
4.9/5
(68)
Which of the following is not usually necessary in order to have an effective MRP system?
(Multiple Choice)
4.8/5
(82)
Comparing known and expected capacity requirements with projected capacity availability is the job of:
(Multiple Choice)
4.8/5
(87)
Capacity requirements planning helps managers reconcile __________ with __________.
(Multiple Choice)
4.8/5
(84)
Lot-for-lot ordering in MRP eliminates the holding costs for parts that are carried over to other periods.
(True/False)
4.9/5
(81)
Which of the following lot sizing methods does not attempt to balance ordering (or setup) and holding costs?
(Multiple Choice)
4.8/5
(79)
The following is a list of components required to produce one unit of end item P:
P: 2 As, 3 Bs, 3 Cs
A: 5 Ms, 2 Rs
B: 1 D, 3 Ns
C: 1 T, 4 Ns
M: 1 N
Determine the number of Ns that will be needed to make 60 Ps in each of these cases:
(A) There are currently 10 Ps on hand.
(B) On-hand inventory consists of 15 Ps, 10 As, 20 Bs, 10 Cs, 100 Ns, 300 Ts, and 200 Ms.
The product structure tree is:

(Essay)
4.8/5
(88)
One of the primary output reports of MRP concerns changes to planned orders.
(True/False)
4.9/5
(78)
Which of the following represents an attempt to balance the benefits of stability against the benefits of responding to new information?
(Multiple Choice)
4.8/5
(81)
Independent demand tends to be more "lumpy" than dependent demand, meaning that we need large quantities followed by periods of no demand.
(True/False)
4.8/5
(82)
Given the following data, construct a material requirements plan which will result in 100 units of Parent 1 (P1) at the beginning of week 6, and 200 units of Parent 2 (P2) at the beginning of week 8:
(Essay)
4.9/5
(80)
Which one of the following is not an input in an MRP system?
(Multiple Choice)
4.9/5
(81)
The MRP input stating which end items are to be produced, when they are needed, and what quantities are needed, is the:
(Multiple Choice)
5.0/5
(85)
In an MRP master schedule, the planning horizon is often separated into a series of time periods called: