One of the main purposes of an MRP system is which of the following?

(Multiple Choice)
4.8/5
(85)

If annual demand is 1,000 units, annual holding cost is $0.50 per unit, and the cost per order is $10, what is the EOQ? ______________________________________

(Short Answer)
4.9/5
(80)

"Projected available balance" is a term referring to unsold finished goods inventory.

(True/False)
5.0/5
(71)

Time fences are periods of time having some specified level of opportunity for the customer to make changes.

(True/False)
4.8/5
(70)

Which of the following files allows us to retrace a material requirement upward in the product structure through each level, identifying each parent item that created the demand?

(Multiple Choice)
4.8/5
(64)

The lot-for-lot (L4L) lot-sizing technique minimizes carrying cost by taking into account setup costs and capacity limitations.

(True/False)
4.8/5
(77)

The economic order quantity (EOQ) lot-sizing technique uses the "square root formula" to balance setup cost, carrying cost, and cost of stockouts.

(True/False)
5.0/5
(59)

Which of the following is one of the main purposes of an MRP system?

(Multiple Choice)
4.9/5
(71)

The economic order quantity (EOQ) lot-sizing technique produces or acquires exactly the amount of product that is needed each time period with none carried over into future periods.

(True/False)
4.9/5
(80)

Which of the following is not a lot-sizing technique used in MRP systems?

(Multiple Choice)
4.8/5
(73)

MRP stands for Material Requirements Planning.

(True/False)
4.8/5
(85)

The least unit cost method of lot-sizing adds ordering, stockout, and inventory carrying costs for each trial lot size and divides by the number of units in each lot size, picking the lot size with the lowest unit cost.

(True/False)
5.0/5
(64)

Manufacturing firms maintain bill of materials (BOM) files, which are simply a sequencing of everything that goes into a final product.

(True/False)
4.9/5
(88)

Net change MRP reflects the exact status of each item managed by the system in "real time."

(True/False)
4.8/5
(78)

Low-level coding in MRP indicates the exact status of each item managed by the system in "real time."

(True/False)
4.9/5
(57)

An output of MRP is a bill of materials (BOM) file.

(True/False)
4.8/5
(80)

Projected available balance is the amount of inventory that is expected as of the beginning of a period.

(True/False)
4.9/5
(86)

The three main inputs to an MRP system are the bill of materials, the master schedule, and the inventory records file.

(True/False)
4.9/5
(84)

Which of the following is considered a primary report in an MRP system?

(Multiple Choice)
4.9/5
(71)

Which of the following is considered a secondary report in an MRP system?

(Multiple Choice)
4.8/5
(84)
Showing 61 - 80 of 89
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)