Exam 2: Executing Strategy: Project Management
How does benchmarking improve operations? And give a relevant example.
Benchmarking is evaluating your operations to another companies/persons operations to see where it is they are potentially better at,and where you can implement their actions to improve your own.Benchmarking helps one get better plans to correct their problems/issues,helps save money by looking at another company to improve,and lowers time needed to come up with a new idea to a problem when perhaps another company has faced that issue too,and came up with a solution.An example would be the VHA story found on page 35,how they benchmarked other healthcare providers to improve their claim processing abilities.
Any path that if delayed will delay the completion of the entire project is known as a:
B
Explain the importance of slack time and how it can impact the critical path.
Slack time is the amount of time a project activity may be delayed until where further delay would delay the entire project.Slack time allows a project manager to use resources between activities to help expedite the project.For example projects with slack time can have resources shifted to an activity along the critical path to help facilitate completion,which could result in the project finishing early.
An optimal procedure for organizations to accept projects is to specify a return on investment (ROI)and fund only projects that meet this criterion.
Give an example of a project with the exponential life cycle and describe why this is a good example.
The amount of safety time needed to protect a particular path in a project is less than the sum of the safety times required to protect the individual activities making up the path.
Give an example of a derivative project and explain why your reasoning.
The set of all project activities graphically interrelated through precedence relationships is known as a/an:
Which of the following statement(s)concerning probabilities of completion is/are incorrect?
Both PERT and CPM are based on variations of the __________ chart?
According to Goldratt,to complete a project on time,the highest priority should be given to the:
Describe the two types of project organizational structure were discussed and the advantages of both.
Three phenomena that tend to bias the expected completion time of projects are inflated time estimates,activity time variability with path interdependencies,and resource dependence.
The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its slack.