Multiple Choice
According to Goldratt,to complete a project on time,the highest priority should be given to the:
A) Critical buffer
B) Feeding chain
C) Project buffer
D) Critical chain
E) Slack activities
Correct Answer:

Verified
Correct Answer:
Verified