Which of the following statement(s) concerning probabilities of completion is/are incorrect?


A) Using the variance of each activity,we can compute the likelihood of completing the project in a given time period.
B) The probability of completing a path is found by calculating the standard normal deviate of the desired completion time less the expected completion time.
C) The distribution of a path's completion time will be approximately normally distributed if the path has a large number of activities on it.
D) The individual activity completion times must be normally distributed
E) All of the above are incorrect