Exam 3: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

PERT calculations typically include the duration variance of each activity.What is the purpose of this calculation,i.e.what's the role of variances in PERT analysis?

(Essay)
4.9/5
(85)

Gantt charts give a timeline for each of a project's activities,but they do not adequately illustrate the interrelationships between the activities and the resources.

(True/False)
4.7/5
(81)

In PERT analysis,the identification of the critical path can be incorrect if a noncritical activity takes substantially more than its expected time.

(True/False)
4.8/5
(82)

Identify several advantages of using PERT (and CPM).

(Essay)
4.9/5
(66)

Identify,in order,the six steps basic to both PERT and CPM.

(Essay)
4.9/5
(88)

Describe in words how to calculate a project's standard deviation.What assumption allows that calculation to be accurate?

(Essay)
4.9/5
(84)

The ________ has established a code of ethics especially for project managers.

(Short Answer)
4.8/5
(85)

A project being analyzed by PERT has 38 activities,16 of which are on the critical path.If the estimated time along the critical path is 90 days with a project variance of 25,what is the probability that the project will be completed in 88 days or less?

(Multiple Choice)
4.9/5
(84)

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?

(Multiple Choice)
5.0/5
(72)

In a PERT network,non-critical activities that have little slack need to be monitored closely:

(Multiple Choice)
4.9/5
(93)

The ES of an activity that has only one predecessor is simply the EF of that predecessor.

(True/False)
4.9/5
(77)

Which of the following statements about Bechtel is true?

(Multiple Choice)
5.0/5
(63)

A simple CPM network has five activities,A,B,C,D,and E.A is an immediate predecessor of C and of D.B is also an immediate predecessor of C and of D.C and D are both immediate predecessors of E.Which of the following statements is true?

(Multiple Choice)
4.8/5
(83)

The critical path for the network activities shown below is ________ with duration ________. The critical path for the network activities shown below is ________ with duration ________.

(Multiple Choice)
4.8/5
(75)

Which of the following statements regarding Gantt charts is true?

(Multiple Choice)
4.8/5
(90)

Which of the following is NOT performed by Microsoft Project?

(Multiple Choice)
4.9/5
(90)

A simple CPM network has three activities,A,B,and C.A is an immediate predecessor of B and of C.B is an immediate predecessor of C.The activity durations are A=4,B=3,C=8.

(Multiple Choice)
4.9/5
(78)

The network analysis method that allows activity times to vary is ________.

(Essay)
4.9/5
(95)

Consider the network presented in the following table.Calculate a.All possible paths b.The critical path c.The slack available at any non-critical points d.The minimum project duration Consider the network presented in the following table.Calculate a.All possible paths b.The critical path c.The slack available at any non-critical points d.The minimum project duration

(Essay)
4.8/5
(76)

Which of the following statements regarding PERT times is true?

(Multiple Choice)
4.8/5
(68)
Showing 81 - 100 of 120
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)