Exam 3: Project Management
Exam 1: Operations and Productivity126 Questions
Exam 2: Operations Strategy in a Global Environment119 Questions
Exam 3: Project Management120 Questions
Exam 4: Forecasting141 Questions
Exam 5: Design of Goods and Services118 Questions
Exam 6: Managing Quality123 Questions
Exam 7: Process Strategy108 Questions
Exam 8: Capacity and Constraint Management96 Questions
Exam 9: Location Strategies120 Questions
Exam 10: Layout Strategies146 Questions
Exam 11: Human Resources, job Design, and Work Measurement154 Questions
Exam 12: Supply Chain Management144 Questions
Exam 13: Inventory Management163 Questions
Exam 14: Aggregate Planning and Sop116 Questions
Exam 15: Material Requirements Planning Mrpand Erp113 Questions
Exam 16: Short-Term Scheduling116 Questions
Exam 17: Jit, tps, and Lean Operations115 Questions
Exam 18: Maintenance and Reliability111 Questions
Exam 19: Sustainability in the Supply Chain80 Questions
Exam 20: Statistical Process Control144 Questions
Exam 21: Supply Chain Management Analytics55 Questions
Exam 22: Decision-Making Tools97 Questions
Exam 23: Linear Programming80 Questions
Exam 24: Transportation Models89 Questions
Exam 25: Waiting-Line Models119 Questions
Exam 26: Learning Curves105 Questions
Exam 27: Simulation75 Questions
Select questions type
PERT calculations typically include the duration variance of each activity.What is the purpose of this calculation,i.e.what's the role of variances in PERT analysis?
(Essay)
4.9/5
(85)
Gantt charts give a timeline for each of a project's activities,but they do not adequately illustrate the interrelationships between the activities and the resources.
(True/False)
4.7/5
(81)
In PERT analysis,the identification of the critical path can be incorrect if a noncritical activity takes substantially more than its expected time.
(True/False)
4.8/5
(82)
Describe in words how to calculate a project's standard deviation.What assumption allows that calculation to be accurate?
(Essay)
4.9/5
(84)
The ________ has established a code of ethics especially for project managers.
(Short Answer)
4.8/5
(85)
A project being analyzed by PERT has 38 activities,16 of which are on the critical path.If the estimated time along the critical path is 90 days with a project variance of 25,what is the probability that the project will be completed in 88 days or less?
(Multiple Choice)
4.9/5
(84)
A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?
(Multiple Choice)
5.0/5
(72)
In a PERT network,non-critical activities that have little slack need to be monitored closely:
(Multiple Choice)
4.9/5
(93)
The ES of an activity that has only one predecessor is simply the EF of that predecessor.
(True/False)
4.9/5
(77)
A simple CPM network has five activities,A,B,C,D,and E.A is an immediate predecessor of C and of D.B is also an immediate predecessor of C and of D.C and D are both immediate predecessors of E.Which of the following statements is true?
(Multiple Choice)
4.8/5
(83)
The critical path for the network activities shown below is ________ with duration ________. 
(Multiple Choice)
4.8/5
(75)
Which of the following statements regarding Gantt charts is true?
(Multiple Choice)
4.8/5
(90)
Which of the following is NOT performed by Microsoft Project?
(Multiple Choice)
4.9/5
(90)
A simple CPM network has three activities,A,B,and C.A is an immediate predecessor of B and of C.B is an immediate predecessor of C.The activity durations are A=4,B=3,C=8.
(Multiple Choice)
4.9/5
(78)
The network analysis method that allows activity times to vary is ________.
(Essay)
4.9/5
(95)
Consider the network presented in the following table.Calculate
a.All possible paths
b.The critical path
c.The slack available at any non-critical points
d.The minimum project duration

(Essay)
4.8/5
(76)
Which of the following statements regarding PERT times is true?