A(n)________ is an organization formed to ensure that programs (projects)receive the proper management and attention.

(Short Answer)
4.7/5
(77)

A PERT project has 45 activities,19 of which are on the critical path.The estimated time for the critical path is 120 days.The sum of all activity variances is 64,while the sum of variances along the critical path is 36.What is the probability that the project can be completed between days 108 and 120?

(Multiple Choice)
4.8/5
(76)

In project management,crashing an activity must consider the impact on all paths in the network.

(True/False)
4.8/5
(70)

What is the objective of critical path analysis?

(Essay)
4.8/5
(87)

An activity on a PERT network has these time estimates: optimistic = 2,most likely = 5,and pessimistic = 10.What is its expected activity time?

(Multiple Choice)
4.9/5
(73)

Which of the following statements regarding time-cost tradeoffs in CPM networks is false?

(Multiple Choice)
4.9/5
(76)

Shortening the project's duration by deleting unnecessary activities is called "project crashing."

(True/False)
4.8/5
(86)

Draw the AOA and AON networks for the following project and calculate the minimum project duration. Draw the AOA and AON networks for the following project and calculate the minimum project duration.

(Essay)
4.9/5
(82)

The ________ distribution is used by PERT analysis to calculate expected activity times and variances.

(Multiple Choice)
4.8/5
(89)

Which of these statements regarding time-cost tradeoffs in CPM networks is true?

(Multiple Choice)
4.8/5
(73)

A network consists of the following list.Times are given in weeks. A network consists of the following list.Times are given in weeks.    a.Draw the network diagram. b.Which activities form the critical path? c.How much slack exists at activities A and F? d.What is the duration of the critical path? a.Draw the network diagram. b.Which activities form the critical path? c.How much slack exists at activities A and F? d.What is the duration of the critical path?

(Essay)
4.8/5
(70)

One responsibility of a project manager is to make sure that the project meets its quality goals.

(True/False)
4.7/5
(74)

An activity on a PERT network has these time estimates: optimistic = 2,most likely = 3,and pessimistic = 8.What is its expected activity time and variance?

(Multiple Choice)
4.9/5
(86)

What is the basic difference between PERT and CPM?

(Essay)
4.8/5
(90)

________ is the amount of time an individual activity in a network can be delayed without delaying the entire project.

(Short Answer)
4.7/5
(94)

One phase of a large project is scheduling.

(True/False)
4.9/5
(88)

The main difference between PERT and CPM is that:

(Multiple Choice)
4.8/5
(87)

A network consists of the following list.Times are given in weeks. A network consists of the following list.Times are given in weeks.    a.Draw the network diagram. b.Calculate the expected duration and variance of each activity. c.Calculate the expected duration and variance of the critical path. d.Calculate the probability that the project will be completed in less than 28 weeks. a.Draw the network diagram. b.Calculate the expected duration and variance of each activity. c.Calculate the expected duration and variance of the critical path. d.Calculate the probability that the project will be completed in less than 28 weeks.

(Essay)
4.9/5
(84)

The ________ is the computed longest time path(s)through a network.

(Short Answer)
4.9/5
(82)

A simple CPM network has three activities,D,E,and F.D is an immediate predecessor of E and of F.E is an immediate predecessor of F.The activity durations are D=4,E=3,F=8.

(Multiple Choice)
5.0/5
(79)