Exam 19: Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Which of the following is not a standard measure of schedule performance which can be used to evaluate priority rules?

(Multiple Choice)
4.7/5
(75)

Which of the following priority rules used in scheduling the sequence of production is calculated as the slack time remaining in the schedule divided by the number of remaining operations,with the smallest value being run first?

(Multiple Choice)
4.8/5
(82)

In finite loading no consideration is given directly to whether there is sufficient capacity at the resources required to complete the work,nor is the actual sequence of the work as done by each resource in the work center considered.

(True/False)
4.8/5
(65)

One of the principles of work center scheduling is that,while certainty of standards,routings and so forth is not entirely possible in a shop,certainty should always be an objective to work towards.

(True/False)
4.8/5
(68)

When work is scheduled in detail using the setup and run time required for each order it is called which of the following?

(Multiple Choice)
4.7/5
(91)

The objective of Johnson's rule for job sequencing is to minimize flow time from the beginning of the first job until the completion of the last job.

(True/False)
4.9/5
(86)

Which of the following is a principle of work center scheduling?

(Multiple Choice)
4.9/5
(79)

Assume there are five jobs (i.e. ,A,B,C,D and E)that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 4 days (i.e. ,job A will take 4 more days to complete),B will take 7 days,C will take 8 days,D will take 2 days and E will take 5 days,which job should be scheduled first if you use the SOT priority rule for job sequencing?

(Multiple Choice)
4.9/5
(70)

What is Johnson's Rule?

(Essay)
4.8/5
(75)

For a continuous process type of manufacturing which of the following is the typical production scheduling approach?

(Multiple Choice)
4.8/5
(74)

For a mid-volume type of manufacturing which of the following is the typical production scheduling approach?

(Multiple Choice)
4.8/5
(106)

Which of the following is a priority rule used to schedule the sequence of jobs in a production operation?

(Multiple Choice)
4.7/5
(87)

Assume you are sequencing a job using Johnson's rule.The job requires 3 hours to assemble and then is followed by 2 hours in the painting department.Which of the following is where you would schedule this job?

(Multiple Choice)
4.7/5
(82)

When work is scheduled in detail using the setup and run time required for each order,then theoretically all schedules will be feasible.

(True/False)
4.7/5
(82)

Assume there are five jobs (i.e. ,A,B,C,D and E)that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 3 days (i.e. ,job A will take 3 more days to complete),B will take 9 days,C will take 6 days,D will take 5 days and E will take 8 days.In what order will these jobs be scheduled if using the SOT priority rule for job sequencing?

(Multiple Choice)
4.8/5
(82)

When work has been scheduled in a shop that does not have sufficient resources to complete the schedule on time,the system that generated the schedule is called which of the following?

(Multiple Choice)
4.9/5
(84)

A system that "backward schedules" is designed to determine and report the earliest date an order can be completed.

(True/False)
5.0/5
(69)

Which of the following is not one of the major functions of shop-floor control?

(Multiple Choice)
4.8/5
(92)

In the context of work assignment,what is infinite loading?

(Essay)
4.9/5
(90)

The objectives of work center scheduling include which of the following?

(Multiple Choice)
4.9/5
(85)
Showing 41 - 60 of 69
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)