Exam 19: Scheduling
Exam 1: Introduction to the Field59 Questions
Exam 2: Operations and Supply Strategy61 Questions
Exam 3: Project Management95 Questions
Exam 4: Product and Service Design53 Questions
Exam 5: Strategic Capacity Management52 Questions
Exam 6: Process Analysis50 Questions
Exam 7: Manufacturing Processes42 Questions
Exam 8: Service Processes59 Questions
Exam 9: Six Sigma Quality83 Questions
Exam 10: Supply-Chain Strategy67 Questions
Exam 11: Logistics and Facility Location56 Questions
Exam 12: Lean Manufacturing74 Questions
Exam 13: Operations Consulting Reengineering68 Questions
Exam 14: Enterprise Resource Planning Systems35 Questions
Exam 15: Demand Management and Forecasting105 Questions
Exam 16: Aggregate Sales and Operations Planning64 Questions
Exam 17: Inventory Control100 Questions
Exam 18: Material Requirements Planning111 Questions
Exam 19: Scheduling69 Questions
Exam 20: Constraint Management64 Questions
Exam 21: Linear Programming Using the Excel Solver40 Questions
Exam 22: Learning Curves57 Questions
Exam 23: Job Design Work Measurement61 Questions
Exam 24: Waiting Line Analysis61 Questions
Exam 25: Process Capability and Spc75 Questions
Exam 26: Simulation54 Questions
Select questions type
Which of the following is not a standard measure of schedule performance which can be used to evaluate priority rules?
(Multiple Choice)
4.7/5
(75)
Which of the following priority rules used in scheduling the sequence of production is calculated as the slack time remaining in the schedule divided by the number of remaining operations,with the smallest value being run first?
(Multiple Choice)
4.8/5
(82)
In finite loading no consideration is given directly to whether there is sufficient capacity at the resources required to complete the work,nor is the actual sequence of the work as done by each resource in the work center considered.
(True/False)
4.8/5
(65)
One of the principles of work center scheduling is that,while certainty of standards,routings and so forth is not entirely possible in a shop,certainty should always be an objective to work towards.
(True/False)
4.8/5
(68)
When work is scheduled in detail using the setup and run time required for each order it is called which of the following?
(Multiple Choice)
4.7/5
(91)
The objective of Johnson's rule for job sequencing is to minimize flow time from the beginning of the first job until the completion of the last job.
(True/False)
4.9/5
(86)
Which of the following is a principle of work center scheduling?
(Multiple Choice)
4.9/5
(79)
Assume there are five jobs (i.e. ,A,B,C,D and E)that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 4 days (i.e. ,job A will take 4 more days to complete),B will take 7 days,C will take 8 days,D will take 2 days and E will take 5 days,which job should be scheduled first if you use the SOT priority rule for job sequencing?
(Multiple Choice)
4.9/5
(70)
For a continuous process type of manufacturing which of the following is the typical production scheduling approach?
(Multiple Choice)
4.8/5
(74)
For a mid-volume type of manufacturing which of the following is the typical production scheduling approach?
(Multiple Choice)
4.8/5
(106)
Which of the following is a priority rule used to schedule the sequence of jobs in a production operation?
(Multiple Choice)
4.7/5
(87)
Assume you are sequencing a job using Johnson's rule.The job requires 3 hours to assemble and then is followed by 2 hours in the painting department.Which of the following is where you would schedule this job?
(Multiple Choice)
4.7/5
(82)
When work is scheduled in detail using the setup and run time required for each order,then theoretically all schedules will be feasible.
(True/False)
4.7/5
(82)
Assume there are five jobs (i.e. ,A,B,C,D and E)that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 3 days (i.e. ,job A will take 3 more days to complete),B will take 9 days,C will take 6 days,D will take 5 days and E will take 8 days.In what order will these jobs be scheduled if using the SOT priority rule for job sequencing?
(Multiple Choice)
4.8/5
(82)
When work has been scheduled in a shop that does not have sufficient resources to complete the schedule on time,the system that generated the schedule is called which of the following?
(Multiple Choice)
4.9/5
(84)
A system that "backward schedules" is designed to determine and report the earliest date an order can be completed.
(True/False)
5.0/5
(69)
Which of the following is not one of the major functions of shop-floor control?
(Multiple Choice)
4.8/5
(92)
The objectives of work center scheduling include which of the following?