List and briefly describe the four main processes of project procurement management.

(Essay)
4.9/5
(89)

Which of the following is true of lump-sum contracts?

(Multiple Choice)
4.7/5
(75)

From the buyer's perspective, the _____ is the least desirable among all contracts because the supplier has no incentive to decrease costs.

(Multiple Choice)
4.8/5
(78)

What are the four types of cost-reimbursable contracts? Briefly describe each type.

(Essay)
4.9/5
(86)

A drawback of outsourcing is that:

(Multiple Choice)
4.9/5
(85)

The process of source selection involves evaluating proposals from sellers, choosing the best one, negotiating, and awarding the _____.

(Short Answer)
4.8/5
(75)

A(n) _____ is a document used to solicit proposals from prospective suppliers.

(Multiple Choice)
4.7/5
(74)

A(n) _____ is a mutually binding agreement that obligates the seller to provide the specified products or services and obligates the buyer to pay for them.

(Short Answer)
4.9/5
(87)

In project procurement management, the process of _____ involves determining what to procure, when, and how.

(Multiple Choice)
4.8/5
(68)

Procurement audits are often done during contract closure to identify lessons learned in the entire procurement process.

(True/False)
4.9/5
(89)

Indirect costs are those costs can be traced back to a project in a cost-effective way.

(True/False)
4.9/5
(92)

The final process in project procurement management is _____.

(Short Answer)
4.8/5
(86)

"Most organizations are not in business to provide information technology services, yet many have spent valuable time and resources on information technology functions when they should have instead worked on important competencies such as marketing, customer service, and new product design. Outsourcing helps tackle this problem." Which of the following benefits does outsourcing primarily provide in such a scenario?

(Multiple Choice)
4.7/5
(72)

In project procurement management, the process of _____ involves obtaining seller responses, selecting sellers, and awarding contracts.

(Multiple Choice)
4.8/5
(84)

In an FPI contract, all of the risk is borne by the buyer.

(True/False)
4.8/5
(92)

In project procurement management, the process of conducting procurements is part of the _____ process.

(Multiple Choice)
4.8/5
(86)

"A shortage of qualified personnel is one of the main reason that companies outsource. A project may require experts in a particular field for several months and planning for this procurement ensures that the needed services will be available for the project." Which of the following benefits does this characteristic of outsourcing provide an organization?

(Multiple Choice)
4.8/5
(83)

With a(n) _____ contract, the buyer pays the supplier for allowable performance costs plus a fixed fee payment usually based on a percentage of estimated costs.

(Multiple Choice)
4.9/5
(75)

An FP-EPA contract carries the least risk for a supplier.

(True/False)
4.8/5
(83)

"Outsourcing to provide extra workers during periods of peak workloads can be much more economical than trying to fill entire projects with internal resources." Which of the following advantages does this characteristic of outsourcing provide organizations?

(Multiple Choice)
4.9/5
(90)