The network below represents a project being analyzed by Critical Path Methods. Activity durations are A=5, B=2, C=12, D=3, E=5, F=1, G=7, H=2, I=10, and J=6. The network below represents a project being analyzed by Critical Path Methods. Activity durations are A=5, B=2, C=12, D=3, E=5, F=1, G=7, H=2, I=10, and J=6.     a. What task must be on the critical path, regardless of activity durations? b. What is the duration of path A-B-E-H-J? c. What is the critical path of this network? d. What is the length of the critical path? e. What is slack time at activity H? f. What is the Late Finish of activity H? g. If activity C were delayed by two time units, what would happen to the project duration? a. What task must be on the critical path, regardless of activity durations? b. What is the duration of path A-B-E-H-J? c. What is the critical path of this network? d. What is the length of the critical path? e. What is slack time at activity H? f. What is the Late Finish of activity H? g. If activity C were delayed by two time units, what would happen to the project duration?

(Essay)
4.8/5
(80)

In a PERT network, non-critical activities that have little slack need to be monitored closely

(Multiple Choice)
4.8/5
(86)

A diagram of all activities and the precedence relationships that exist between these activities in a project is a(n) __________.

(Short Answer)
4.9/5
(72)