Exam 17: Material Requirements Planning MRP and ERP
Exam 1: Operations and Productivity126 Questions
Exam 2: Operations Strategy in a Global Environment135 Questions
Exam 3: Project Management123 Questions
Exam 4: Forecasting144 Questions
Exam 5: Design of Goods and Services137 Questions
Exam 6: Managing Quality130 Questions
Exam 7: Statistical Process Control154 Questions
Exam 8: Process Strategy131 Questions
Exam9: Capacity and Constraint Management107 Questions
Exam 10: Location Strategies140 Questions
Exam 11: Layout Strategies161 Questions
Exam 12: Human Resources, Job Design, and Work Measurement191 Questions
Exam 13: Supply-Chain Management145 Questions
Exam 14: Outsourcing as a Supply-Chain Strategy73 Questions
Exam 15: Inventory Management155 Questions
Exam 16: Aggregate Planning134 Questions
Exam 17: Material Requirements Planning MRP and ERP169 Questions
Exam 18: Short-Term Scheduling139 Questions
Exam 19: Just-In-Time and Lean Options137 Questions
Exam 20: Maintenance and Reliability130 Questions
Exam 21: Decision-Making Tools97 Questions
Exam 22: Linear Programming100 Questions
Exam 23: Transportation Models94 Questions
Exam 24: Waiting-Line Models135 Questions
Exam 25: Learning Curves111 Questions
Exam 26: Simulation93 Questions
Select questions type
A bill of material must be updated with the corrected dimensions of a part. The document that details this change is a(n)
Free
(Multiple Choice)
4.8/5
(65)
Correct Answer:
B
The Wagner-Whitin algorithm is the most widely used MRP lot-sizing technique.
Free
(True/False)
4.9/5
(89)
Correct Answer:
False
In MRP record calculations, the appearance of a negative value for the gross requirements of an end item in a specific time bucket
Free
(Multiple Choice)
4.9/5
(79)
Correct Answer:
D
All of the following are advantages of enterprise resource planning (ERP) except it
(Multiple Choice)
4.9/5
(81)
The lot-for-lot lot-sizing technique is particularly appropriate when demand is not very smooth and set up cost is small compared to holding cost.
(True/False)
4.9/5
(84)
Linking a part requirement with the parent component that caused the requirement is referred to as
(Multiple Choice)
4.8/5
(78)
Construct an indented bill of material for a common 3-ring view binder (the kind that lets you slip your own cover sheet into the front panel and spine). Assume the rings to be 1 inch diameter. Don't worry about other dimensions?
pay attention to accounting for all of the parts.
(Essay)
4.8/5
(81)
It is week 1 and there are currently 20 As in stock. The MPS calls for 300 As at the start of week 5. If there are scheduled receipts planned for week 3 and week 4 of 120 As each and A has a lead time of 1 week when and how large of an order should be placed to meet the requirement of 300 As?
(Multiple Choice)
4.8/5
(71)
Given the following bill of material
If the demand for product A is 50 units, what will be the gross requirement for component E?
(Multiple Choice)
4.9/5
(87)
Explain what is meant by "nervousness" of the MRP schedule. Provide an example. Name two tools that are particularly useful in reducing system nervousness in MRP systems.
(Essay)
5.0/5
(75)
The aggregate plan gets input or feedback from which of the following areas?
(Multiple Choice)
4.9/5
(79)
DRP is a time-phased stock-replenishment plan for all levels of a distribution network.
(True/False)
4.8/5
(91)
A working MRP system allows a firm to react to even minor changes in production requirements. Discuss both the advantages and disadvantages of having such ability.
(Essay)
4.9/5
(75)
Which of the following statements regarding lot-sizing is true?
(Multiple Choice)
4.8/5
(73)
The Aggregate Plan, derived from the Master Production Schedule, specifies in more detail how much of which products is to be made at what times.
(True/False)
4.8/5
(86)
Consider the following requirements for a certain product.
Period 1 2 3 4 5 6 7 8 Grossrequirements 0 200 200 500 0 400 0 400
Beginning inventory = 500 units
Setup cost = $500 per setup
Lead time = 1 week
Holding cost = $3 per unit per week
a. Develop the lot-for-lot MRP table.
b. Calculate the total relevant costs.
(Essay)
4.8/5
(78)
The __________ is used to correct an erroneous dimension, quantity, or other specification in a bill of material.
(Short Answer)
4.8/5
(75)
The MPS calls for 110 units of Product A. There are currently 60 of Product A on hand. Each A requires 2 of Part B. There are 30 units of B available.
a. Calculate the net requirements for A.
b. Calculate the gross requirements for B.
c. Calculate the net requirements for B.
(Essay)
4.9/5
(84)
A(n) __________ system is packaged business software that automates and integrates the majority of their business processes, shares common data and practices across the entire enterprise, and produces and accesses information in a real-time environment.
(Short Answer)
4.7/5
(94)
Showing 1 - 20 of 169