The quantity required of a dependent demand item is computed from the demand for the final products in which the item is used.

(True/False)
5.0/5
(82)

MRP is generally practiced on items with dependent demand.

(True/False)
4.8/5
(88)

Consider the following bill of material. Forty units of Product A are needed. Assuming no on-hand inventory, and no scheduled receipts, explode the bill of material. Consider the following bill of material. Forty units of Product A are needed. Assuming no on-hand inventory, and no scheduled receipts, explode the bill of material.

(Essay)
4.9/5
(71)

Four A washers, Five B washers, Two C bolts, and a D bolt are required to make one Grill parts kit. If 100 grill part kits are needed how many more washers will be consumed than bolts?

(Essay)
4.7/5
(67)

A company is trying to implement MRP but is having trouble determining which order sizing method will minimize costs. Setup cost is $200 and holding cost is $2/period. If each period is 1 week, gross requirements are 270 units per 10 weeks, and there are 6 planned order releases for every 10 weeks, calculate the cost for lot-for-lot compared to EOQ for an entire year. Assume that EOQ and lot-for-lot are computed as though the usage will occur continually throughout the year.

(Essay)
4.7/5
(79)

Wheeled Coach uses __________ as the catalyst for low inventory, high quality, tight schedules, and accurate records.

(Short Answer)
4.8/5
(74)

Each R requires 2 of component S and 1 of part T. The lead time for assembly of R is 3 days. The lead time for the manufacture of S is 5 days. The lead time for the manufacture of T is 10 days. The cumulative lead time for R is __________ days.

(Multiple Choice)
4.7/5
(74)

Firms may discover that, rather than adapting ERP to the way they do business, they have to adapt the way they do business to accommodate the ERP software.

(True/False)
4.7/5
(70)

What are time fences? Why are they used?

(Essay)
4.8/5
(70)

One of the tools that is particularly useful in reducing the system nervousness in the MRP system is (are)

(Multiple Choice)
4.7/5
(85)

The __________ is the input to material requirements planning which lists the assemblies, subassemblies, parts, and raw materials needed to produce one unit of finished product.

(Multiple Choice)
4.9/5
(91)

Describe finite capacity scheduling. How is it more realistic than MRP?

(Essay)
4.8/5
(73)

If a load report (resource requirements profile) shows a work center scheduled beyond capacity

(Multiple Choice)
4.8/5
(71)

Which of the following is False concerning enterprise resource planning (ERP)?

(Multiple Choice)
4.9/5
(74)

While ERP may provide a strategic advantage over competitors, it is so complex that many companies cannot adjust to it.

(True/False)
4.8/5
(93)

MRP is an excellent tool for scheduling products with variable lead times.

(True/False)
4.8/5
(87)

Which of the following regarding enterprise resource planning (ERP) is true?

(Multiple Choice)
4.9/5
(75)

Effective use of MRP and other dependent demand models does not require which of the following?

(Multiple Choice)
4.8/5
(87)

Distortion in MRP systems can be minimized when safety stock is held at the

(Multiple Choice)
4.7/5
(86)

The MPS calls for 50 units of Product A and 60 of B. There are currently 35 of Product B on hand. Each A requires 2 of Part C; each B requires 5 of C. There are 160 units of C available. a. Calculate the net requirements for B. b. Calculate the gross requirements for C. c. Calculate the net requirements for C.

(Essay)
4.9/5
(90)