Exam 3: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

By their very nature, projects have a limited lifetime, and that sets project management apart from the management of more traditional activities.

(True/False)
4.8/5
(85)

A project manager is interested in crashing a project with variable activity times. Which of the following tools should he/she employ?

(Multiple Choice)
4.8/5
(84)

Draw the AOA and AON networks for the following project and calculate the minimum project duration. Activity Duration (days) Immediate Predecessors A 10 -- B 8 -- C 2 D 4 E 5 ,,

(Essay)
4.8/5
(78)

The shortest of all paths through the network is the critical path.

(True/False)
4.9/5
(78)

Consider the network presented in the following table. Calculate a. All possible paths b. The critical path c. The slack available at any non-critical points d. The minimum project duration Task Duration (Days) Immediate Predecessors A 5 None B 3 A C 4 A D 2 C E 1 B,D

(Essay)
4.9/5
(68)

__________ is decreasing activity time in a network to reduce time on the critical path so total completion time is reduced.

(Short Answer)
4.9/5
(86)

__________ is a network technique using only one time factor per activity that enables managers to schedule, monitor, and control large and complex projects.

(Short Answer)
4.9/5
(82)

The expected activity time in PERT analysis is calculated as

(Multiple Choice)
4.7/5
(76)

The network below represents a project being analyzed by Critical Path Methods. Activity durations are indicated on the network. The network below represents a project being analyzed by Critical Path Methods. Activity durations are indicated on the network.     a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration? a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity H. d. If activity I were delayed by ten time units, what would be the impact on the project duration?

(Essay)
4.9/5
(82)

What is the objective of critical path analysis?

(Essay)
4.9/5
(84)

One phase of a large project is scheduling.

(True/False)
4.9/5
(90)

PERT calculations typically include the duration variance of each activity. What is the purpose of this calculation-what's the role of variances in PERT analysis?

(Essay)
5.0/5
(61)

How is the expected completion time of a project activity, and of a PERT project, computed?

(Essay)
4.8/5
(79)

The Beta distribution is used in project management to

(Multiple Choice)
4.9/5
(79)

Which of the following statements regarding project management is False?

(Multiple Choice)
4.9/5
(74)

What is the basic difference between PERT and CPM?

(Essay)
4.9/5
(80)

A code of ethics especially for project managers

(Multiple Choice)
4.9/5
(86)

Every network has at least one critical path.

(True/False)
4.9/5
(64)

Which of the following statements regarding CPM networks is true?

(Multiple Choice)
4.8/5
(78)

A project organization works best for an organization when the project resides in only one of its functional areas.

(True/False)
4.9/5
(73)
Showing 21 - 40 of 123
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)