The __________ distribution is used by PERT analysis to calculate expected activity times and variances.

(Multiple Choice)
4.7/5
(66)

The ES of an activity that has only one predecessor is simply the EF of that predecessor.

(True/False)
4.7/5
(81)

A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A -- 8 B -- 3 C A 7 D A, B 3 E C 4 a. Draw the network diagram. b. Calculate the ES, EF, LS, LF, and Slack for each activity. c. What is project completion time?

(Essay)
4.8/5
(81)

The time an activity will take assuming very unfavorable conditions is

(Multiple Choice)
4.7/5
(80)

A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=8.

(Multiple Choice)
5.0/5
(77)

Describe some of the challenges faced in the construction of the new 11-story building at Arnold Palmer Hospital in Orlando, Florida.

(Essay)
4.7/5
(77)

Work Breakdown Structure is a useful tool in project management because it addresses the timing of individual work elements.

(True/False)
4.8/5
(82)

A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, the probability that the project will be completed in 95 days or less is

(Multiple Choice)
4.8/5
(73)

Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity __________ should be crashed first, adding __________ to project cost. Activity Normal Time Normal Cost Crash Time Crash Cost One 8 days \ 6,000 6 days \ 6,800 Two 10 days \ 4,000 9 days \ 5,000

(Multiple Choice)
4.8/5
(80)

Which of the following statements regarding time-cost tradeoffs in CPM networks is False?

(Multiple Choice)
4.7/5
(81)

A combination of effective Gantt chart use and other tactics allowed Delta to cut the average time for a plane layover by what % of the original 60 minute duration?

(Multiple Choice)
4.7/5
(81)

Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. Activity Normal Time Normal Cost Crash Duration Crash Cost A 9 days \ 8,000 7 days \ 12,000 B 5 days \ 2,000 3 days \ 10,000 C 12 days \ 9,000 11 days \ 12,000 a. What is the crash cost per unit time for activity A? b. What is the crash cost per unit time for activity B? c. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? d. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost? e. Assuming no other paths become critical, how much can this project be shortened at what total added cost?

(Essay)
4.7/5
(74)

Ethical issues which can arise in projects include gifts from contractors, pressure to mask delays with False status reports, and pressure to compromise project quality for cost or time savings.

(True/False)
4.7/5
(89)

Which of the following statements regarding critical paths is true?

(Multiple Choice)
4.8/5
(63)

Briefly describe the concept of cost/time trade-off and how it is used.

(Essay)
4.9/5
(80)

Explain why the critical path is the longest, not the shortest, path through a network.

(Essay)
4.8/5
(87)

The project organization works best when which of the following conditions are satisfied? I. Work can be defined with a specific goal and deadline. II. The job is typical and familiar to the existing organization. III. The work contains interrelated tasks requiring specialized skills IV. The project is temporary but unimportant to long-term organizational success V. The project cuts across organizational lines.

(Multiple Choice)
4.9/5
(84)

__________ divides a project into more and more detailed components.

(Short Answer)
4.9/5
(84)

The difference between AON and AOA networks is that

(Multiple Choice)
4.9/5
(72)

What are the advantages of using PERT and CPM?